Title:
|
| | |
FINDING: EXEMPTION SECTIONS
|
|
Wording
|
| | |
The proposal is consistent with Exemptons Section 3.402(1), of the Jefferson-Port Townsend Shoreline Management Master Program.
|
|
|
Title:
|
| | |
FINDING: HPA NUMBER
|
|
Wording
|
| | |
A Hydraulic Project Approval was issued __________________ under Control Number _____________________. The HPA expires on _________ .
|
|
|
Title:
|
| | |
fish enhancement
|
|
Wording
|
| | |
This proposal is a fish-enhancement project; wild chum salmon will be temporarily held in the net pens and released after a 29-day "weight gain program". This is not a commercial net-pen (feed is letss than 5,000lbs/month, no harvesting of fish); and as such, does not require a waste discharge permit from Department of Ecology.
|
|
|
Title:
|
| | |
APPROVAL ONLY FOR J-PTSMMP
|
|
Wording
|
| | |
This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.
|
|
|
Title:
|
| | |
OTHER WORK/SEPARATE APPROVAL
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Program other than as described above shall receive separate review from this office.
|
|
|
Title:
|
| | |
NO FILL OR OTHER MATERIAL
|
|
Wording
|
| | |
No fill or other material may be placed in the waters or intertidal areas of Jefferson County.
|
|
|
Title:
|
| | |
NOTIFICATION PRIOR TO BEGINNING
|
|
Wording
|
| | |
The proponent shall notify the Jefferson County Permit Center, (360) 379-4450, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.
|
|
|
Title:
|
| | |
public's normal use
|
|
Wording
|
| | |
The proposed project shall not interfere with the public's normal use of the water.
|
|
|
Title:
|
| | |
temporary only
|
|
Wording
|
| | |
The proposed project shall be temporary as stated on the application. The applicant shall notify the Jefferson County Permit Center (360-379-4450) upon conclusion of the described project; and the net-pens shall be removed after April 13, 1998.
|
|
|
Title:
|
| | |
notify with change
|
|
Wording
|
| | |
Should the project extend past the 29-day period; involve distributing more than 5,000 lbs of feed per month; and/or raise more than 20,000 fish, the applicant shall notify the Permit Center and the Department of Ecology Water Qaulity Program (360-407-6098) immediately.
|
|
|
Title:
|
| | |
corps
|
|
Wording
|
| | |
The applicant shall notify the U.S.Army Corps of Engineers to determine if the project is within navigable waters.
|
|