Permit Case Summary

Case Number: Search Help

Case Number:XMP1997-00069 Case Status: Date Received:11/10/1997
Description:As part of a Discovery Bay summer chum restoration project, fry are reared short term (less than 30 days) in salt water net pens in order to provide an advantage for better survival. This request is to permit 2 net pens to be attached to an existing dock. Two nets are necessary in order to accommodate different egg takes and release timings. The net pens are to be placed partly beneath an existing pier and ramp which purpose is to minimize shading of the bay floor. Plans and specifications are provided. Date Issued:12/31/1997
Applicant: WILD OLYMPIC SALMON Expiration Date:12/31/1998 12:00:00 AM
Site Address: Case Finaled:
Parcel No:901182036 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: (F) Issue exemption
Date Completed: 12/31/1997
Disposition: F
Description: Planner Review
Date Completed: 12/31/1998
Disposition: F

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: FINDING: EXEMPTION SECTIONS
Wording The proposal is consistent with Exemptons Section 3.402(1), of the Jefferson-Port Townsend Shoreline Management Master Program.

Title: FINDING: HPA NUMBER
Wording A Hydraulic Project Approval was issued __________________ under Control Number _____________________. The HPA expires on _________ .

Title: fish enhancement
Wording This proposal is a fish-enhancement project; wild chum salmon will be temporarily held in the net pens and released after a 29-day "weight gain program". This is not a commercial net-pen (feed is letss than 5,000lbs/month, no harvesting of fish); and as such, does not require a waste discharge permit from Department of Ecology.

Title: APPROVAL ONLY FOR J-PTSMMP
Wording This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.

Title: OTHER WORK/SEPARATE APPROVAL
Wording Work within the jurisdiction of the Shoreline Program other than as described above shall receive separate review from this office.

Title: NO FILL OR OTHER MATERIAL
Wording No fill or other material may be placed in the waters or intertidal areas of Jefferson County.

Title: NOTIFICATION PRIOR TO BEGINNING
Wording The proponent shall notify the Jefferson County Permit Center, (360) 379-4450, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.

Title: public's normal use
Wording The proposed project shall not interfere with the public's normal use of the water.

Title: temporary only
Wording The proposed project shall be temporary as stated on the application. The applicant shall notify the Jefferson County Permit Center (360-379-4450) upon conclusion of the described project; and the net-pens shall be removed after April 13, 1998.

Title: notify with change
Wording Should the project extend past the 29-day period; involve distributing more than 5,000 lbs of feed per month; and/or raise more than 20,000 fish, the applicant shall notify the Permit Center and the Department of Ecology Water Qaulity Program (360-407-6098) immediately.

Title: corps
Wording The applicant shall notify the U.S.Army Corps of Engineers to determine if the project is within navigable waters.