Title:
|
| | |
FINDING: EXEMPTION SECTIONS
|
|
Wording
|
| | |
The proposal is consistent with Exemptons Section 3.402(6) of the Jefferson-Port Townsend Shoreline Management Master Program.
|
|
|
Title:
|
| | |
FINDING: HPA NUMBER
|
|
Wording
|
| | |
A Hydraulic Project Approval was issued July 8, 1997, underControl Number 00-D0564-01. The HPA expires on September 30, 1997.
|
|
|
Title:
|
| | |
new information submitted
|
|
Wording
|
| | |
This permit exemption includes a modification of the project despcription which was approved in the exemption issued on August 26, 1997. The modification includes provisions to maintain the existing structure (the culvert) by excavating the gravel deposit within the culvert.
|
|
|
Title:
|
| | |
APPROVAL ONLY FOR J-PTSMMP
|
|
Wording
|
| | |
This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.
|
|
|
Title:
|
| | |
OTHER WORK/SEPARATE APPROVAL
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Program other than as described above shall receive separate review from this office.
|
|
|
Title:
|
| | |
NO FILL OR OTHER MATERIAL
|
|
Wording
|
| | |
No fill or other material may be placed in the waters or intertidal areas of Jefferson County.
|
|
|
Title:
|
| | |
NOTIFICATION PRIOR TO BEGINNING
|
|
Wording
|
| | |
The proponent shall notify the Jefferson County Permit Center, (360) 379-4450, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
All conditions of the HPA shall be followed.
|
|