Title:
|
| | |
FINDING: EXEMPTION SECTIONS
|
|
Wording
|
| | |
The proposal is consistent with Exemptons Section 3.402(1) of the Jefferson-Port Townsend Shoreline Management Master Program.
|
|
|
Title:
|
| | |
FINDING: HPA NUMBER
|
|
Wording
|
| | |
A Hydraulic Project Approval was issued by Department of Fish and Wildlife under Control Number 00-C6654-01 and expires on July 30, 1997.
|
|
|
Title:
|
| | |
CUSTOM FINDING
|
|
Wording
|
| | |
This proposal is a fish-enhancement project; wild chum salmon will be temporarily held in the net pens and released after a 28-day "fattening-up period". This is not a commercial net-pen (feed is less than 5,000 lbs/month); and as such, does not require a waste discharge permit from Dept.of Ecology.
|
|
|
Title:
|
| | |
APPROVAL ONLY FOR J-PTSMMP
|
|
Wording
|
| | |
This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.
|
|
|
Title:
|
| | |
OTHER WORK/SEPARATE APPROVAL
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Program other than as described above shall receive separate review from this office.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
The proposed project shall not interfere with the public's normal use of the water.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
The proposed project shall be temporary as stated on the application. The applicant shall notify the Jefferson County Permit Center (360-379-4464) upon conclusion of the described project; and the net-pens shall be removed after May 2, 1997.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
Should the project extend past 30-days; involve feeding more than 5,000 lbs/month; and/or raise more than 20,000 fish; the applicant shall inform the Permit Center and the Dept.of Ecology Water Quality Program (360) 407-6098 of this change.
|
|