Permit Case Summary

Case Number: Search Help

Case Number:XMP1996-00058 Case Status: Date Received:8/23/1996
Description:Remove accumulated sediment & gravel from the channel of Snow Creek. From 200 ft. upstream from the SR101 bridge to a point approx. 900 ft. downstream from the SR20 bridge (approx. 1200 ft.) the channel will be excavated to a depth of no more than six vertical feet below present streambed elevation. Habitat pools will be excavated to a depth of approximately 3 ft. below adjacent streambed elevation. Tracked excavator will be used operating from the bank. Between the SR 101 bridge upstream to the WDF&W Research Station weir (approx. 2000 ft) existing pools may be excavated to a maximum depth of 6 ft. & existing riffle areas to a maximum depth of 3 ft. below present elevation. Additional habitat pools may be excavated to create additional habitat, depending on WDFW recommendations. Large woody debris (LWD) to provide fish habitat will be placed and securely anchored in all existing pools where excavation occurs and in all newly created pools upstream of SR 101. LWD placement will occur at a rate of at least two rootwads and one log per pool. All LWD will be coniferous material in sound, rot free condition. Revegetation of stream- banks will occur where necessary. Conifers will be used as much as possible. The operation of the WDF&W weir will be altered to catch additional sediment/ gravel, to control the streambed aggradation in the project area. This material will be removed as needed. Existing bypass structures may be modified to accommodate greater flow for water quality protection. In stream activities will occur between June 15 and September 15 to minimize impacts on salmon & steelhead. All work including LWD size/ placement & pool locations shall be subject to the conditions of Wash. Dept. of Fish & Wildlife (WDFW) in the required HPA. Date Issued:11/2/1996
Applicant:PHILIP ZERR Expiration Date:11/2/1997 12:00:00 AM
Site Address:31 FAIRMOUNT RD Case Finaled:
Parcel No:902243044 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: Planner Review
Date Completed:
Disposition:
Description: (F) Issue exemption
Date Completed: 8/23/1996
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: FINDING: EXEMPTION SECTIONS
Wording The proposal is consistent with HB5155 and the Jefferson-Port Townsend Shoreline Management Master Program. The proposal is not a substantial development.

Title: FINDING: HPA NUMBER
Wording A Hydraulic Project Approval was issued August 18, 1995 under Control Number 00-A1590-02. The HPA expires on April 15, 1997.

Title: APPROVAL ONLY FOR J-PTSMMP
Wording This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.

Title: OTHER WORK/SEPARATE APPROVAL
Wording Work within the jurisdiction of the Shoreline Program other than described above shall receive separate review and approval from this office.

Title: NO FILL OR OTHER MATERIAL
Wording No fill or other material may be placed in the waters or intertidal areas of Jefferson County.

Title: FISHERIES & HYDRAULICS CODE
Wording Prior to commencing construction, proponent should contact the Washington State Department of Fisheries at 895-4757 to determine whether this action is subject to the Washington State Hydraulics Code.

Title: NOTIFICATION PRIOR TO BEGINNING
Wording The proponent shall notify the Jefferson County Permit Center, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.

Title: CUSTOM CONDITION
Wording The proponent shall comply with the provisions set forth in the Hydraulic permit No. 00-A1590-02.