Title:
|
| | |
FINDING: EXEMPTION SECTIONS
|
|
Wording
|
| | |
The proposal is consistent with Exemptons Section 3.402(6) of the Jefferson-Port Townsend Shoreline Management Master Program. The proposal is not a substantial development.
|
|
|
Title:
|
| | |
FINDING: MDNS ISSUED
|
|
Wording
|
| | |
Reviewed under SEPA pursuant to WAC 197-11-340(2) by Washington State Parks and Recreation Commission acting as lead agency. A Determination of Non-significance was issued by the Department on August 22, 1996.
|
|
|
Title:
|
| | |
APPROVAL ONLY FOR J-PTSMMP
|
|
Wording
|
| | |
This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.
|
|
|
Title:
|
| | |
OTHER WORK/SEPARATE APPROVAL
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Program other than described above shall receive separate review and approval from this office.
|
|
|
Title:
|
| | |
FISHERIES & HYDRAULICS CODE
|
|
Wording
|
| | |
Prior to commencing construction, proponent should contact the Washington State Department of Fisheries at 895-4757 to determine whether this action is subject to the Washington State Hydraulics Code.
|
|
|
Title:
|
| | |
NOTIFICATION PRIOR TO BEGINNING
|
|
Wording
|
| | |
The proponent shall notify the Jefferson County Permit Center, (360) 379-4450, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.
|
|
|
Title:
|
| | |
RIPRAP ALIGNED WITH OHW
|
|
Wording
|
| | |
The riprap shall be placed as close to the bank as practicable and in substantial alignment with the ordinary high water mark.
|
|