Title:
|
| | |
FINDING: EXEMPTION SECTIONS
|
|
Wording
|
| | |
The proposal is consistent with Exemptons Section 3.402(6) and Section 5.70 "Dredging" of the Jefferson-Port Townsend Shoreline Management Master Program. The proposal is not a substantial development.
|
|
|
Title:
|
| | |
FINDING: HPA NUMBER
|
|
Wording
|
| | |
A Hydraulic Project Approval was issued August 10, 1993 under Control Number 01-87879-01. Per a letter dated June 1, 1994 from the Department of Fish and Wildlife the time limitations on the above HPA are changed to June 1, 1994 thru June 1, 1999. The HPA expires on June 1, 1999.
|
|
|
Title:
|
| | |
CUSTOM FINDING
|
|
Wording
|
| | |
The initial proposal for constructing the low water bypass was reviewed under SDP88-0009. A Determination of Non Significance was issued by Jefferson County on June 8, 1989.
|
|
|
Title:
|
| | |
APPROVAL ONLY FOR J-PTSMMP
|
|
Wording
|
| | |
This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.
|
|
|
Title:
|
| | |
OTHER WORK/SEPARATE APPROVAL
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Program other than described above shall receive separate review and approval from this office.
|
|
|
Title:
|
| | |
NOTIFICATION PRIOR TO BEGINNING
|
|
Wording
|
| | |
The proponent shall notify the Jefferson County Permit Center, Development Review Division 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
The proponent shall comply with the conditions 1-7 as set forth in the Hydraulic Project Approval (Control No. 01-87879-01).
|
|