Case Number:XMP1994-00001 Case Status: Date Received:12/30/1993
Description:PROPOSAL: Routine dock maintenance. Replace dock fender piles at the PECO dock and debris wall planking at the casual dock located at the Port Townsend Paper Mill. Date Issued:1/5/1994
Applicant: PT PAPER CORP Expiration Date:1/5/1995 12:00:00 AM
Site Address: MILL SITE Case Finaled:
Parcel No:001152006 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: (F) Issue exemption
Date Completed: 1/5/1994
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: FINDING: EXEMPTION SECTIONS
Wording The proposal is consistent with Exemptons Section 3.402(6) of the Jefferson-Port Townsend Shoreline Management Master Program. The proposal is not a substantial development.

Title: FINDING: MDNS ISSUED
Wording Reviewed under SEPA by Jefferson County acting as lead agency. Mitigated Determination of Non-significance issued by Jefferson County Board of Commissioners on November 21, 1988.

Title: APPROVAL ONLY FOR J-PTSMMP
Wording This approval pertains to Jefferson-Port Townsend Shoreline Management Master Program requirements only. The approval of any other agency with jurisdiction or any other required permits shall be obtained prior to undertaking the project.

Title: OTHER WORK/SEPARATE APPROVAL
Wording Work within the jurisdiction of the Shoreline Program other than described above shall receive separate review and approval from this office.

Title: NO FILL OR OTHER MATERIAL
Wording No fill or other material may be placed in the waters or intertidal areas of Jefferson County.

Title: FISHERIES & HYDRAULICS CODE
Wording Prior to commencing construction, proponent should contact the Washington State Department of Fisheries at 895-4757 to determine whether this action is subject to the Washington State Hydraulics Code.

Title: NOTIFICATION PRIOR TO BEGINNING
Wording The proponent shall notify the Jefferson County Planning and Building Department 48 hours in advance prior to commencing construction in order to allow monitoring and ensure conformance with project conditions.