Permit Case Summary

Case Number: Search Help

Case Number:SUB2006-00001 Case Status:Finaled Date Received:1/30/2006
Description:Boundary Line Adjustment Date Issued:4/10/2006
Applicant:RICHARD BRODERS Expiration Date:10/10/2006 12:00:00 AM
Site Address: .................... Case Finaled:9/26/2006
Parcel No:996400909 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 10/6/2006
Disposition: DONE
Description: Final Plat RECORDED Status "F"
Date Completed: 9/26/2006
Disposition: DONE
Description: Assessor finl plat sgn off
Date Completed: 9/26/2006
Disposition: DONE
Description: Approve Permit-UF
Date Completed: 4/10/2006
Disposition: DONE
Description: DECISION APPROVAL (Status "A")
Date Completed: 4/10/2006
Disposition: DONE
Description: Review Complete-U
Date Completed: 4/10/2006
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 2/6/2006
Disposition: DONE
Description: Case Entered
Date Completed: 1/30/2006
Disposition:
Description: Date Assigned to Planner
Date Completed: 1/30/2006
Disposition:
Description: Septic Review Complete-U
Date Completed: 4/10/2006
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 2/6/2006
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 2/6/2006
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 2/6/2006
Disposition: DONE
Description: Consistency Review-U
Date Completed: 4/10/2006
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 4/10/2006
Disposition: DONE
Description: SITE INSPECTION COMPLETE
Date Completed: 1/30/2006
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: C-EH CONDITION
Wording Sewage disposal systems have not been approved for the lots, parcels or tracts contained within the Boundary Line Adjustment. Onsite sewage disposal systems shall meet design standards and regulatory requirements in effect at the time of application for a sewage disposal permit. Any removal of or major disturbances of soil within the proposed drainfield areas may create site conditons that are unacceptable for the installation of sewage disposal systems.

Title: C-NOTICE TO PUBLIC
Wording The following notice shall be placed on the final survey mylar: JEFFERSON COUNTY NOTICE TO PUBLIC This Boundary Line Adjustment does not guarantee that each resulting parcel has adequate soils to support on-site septic nor does this Boundary Line Adjustment guarantee that each resulting parcel is guaranteed a buildable area. Applications for septic and building permits will be reviewed at time of submittal of such application for consistency with current state and county codes and ordinances.

Title: C-APPROVAL NOT GUARANTEE
Wording Approval of this Boundary Line Adjustment does not guarantee the approval of any future county permits and/or approvals.

Title: C-NOTICE TO PUBLIC
Wording The following notice shall be placed on the final survey mylar: JEFFERSON COUNTY NOTICE TO PUBLIC Current Jefferson County Geographic Information System (GIS) maps identify the presence of an Environmentally Sensitive Area (ESA) such as stream, wetland, flood, landslide hazard area, erosion, aquifer recharge area, SIPZ, fish and wildlife habitat, shoreline, etc., lying within and/or adjacent to the revised parcels encompassed by this Boundary Line Adjustment. Prior to any land disturbing activity or construction activity, applicant/owner shall contact the Jefferson County Department of Community Development regarding compliance for such ESA's. Approval of this Boundary Line Adjustment does not guarantee issuance of a building permit within said parcel(s). Such determination is dependent on approvals of water, septic, bulk and dimensional setbacks, and ESA requirements.

Title: C-TAXES PAID
Wording CONSISTENT WITH RCW 84.56.345 CURRENT YEAR AND ALL DELINQUENT PROPERTY TAXES SHALL BE PAID PRIOR TO RECORDING THE STATEMENT OF INTENT.

Title: C-RECORDING
Wording Consistent with JCC Title 18.35.080 (3), the applicant/surveyor is responsible for recording the Statement of Intent with the Jefferson County Auditor and referencing said statement of Intent AFN on the face of the survey.

Title: C-FILED MYLAR
Wording The survey mylar and applicable recording fee payable to the Jefferson County Auditor shall be submitted to the Department of Community Development for department signatures and recording of said mylar.

Title: C-FILED SOI & QCD
Wording An Excise Tax Affidavit will need to be completed for the Statement of Intent. An Excise Tax Affidavit is also required for every document that will be recorded such as Quit Claim Deeds or Statutory Warranty Deeds. It is the applicants' responsibility to file these instruments with Jefferson County Auditor in order to convey the ownership of the adjusted land.

Title: C-REF SOI ON SUREVY
Wording The following statement shall be placed on the face of the final survey mylar: For legal descriptions of Parcels A, B, C, D, E and F before and after Boundary Line Adjustment and the Statements of Intent see AFN ________________.

Title: C-SIGNATURE BLOCK
Wording The final record of survey document shall contain the following signature blocks: (1) The Jefferson County Assessor's Office, and (2) The Department of Community Development.

Title: Seawater Intrusion Areas
Wording To help prevent seawater from intruding landward into underground aquifers, all new development activity on Marrowstone Island, Indian Island and within 1/4 mile of any marine shoreline shall be required to infiltrate all stormwater runoff onsite.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-EH REVIEW
Wording A site inspection was completed on February 21, 2006 by Environmental Health. The soils are type 1, excessively coarse sands and gravel. Half (1/2) acre is required per lot. The soils are suitable for onsite sewage disposal and the lots sizes meet minimum land area requirements for lots using a public water supply assuming the roads are vacated as shown and only easements remain.

Title: F-CONSISTENT WITH
Wording The proposal complies with JCC Title 18.35.060.1(a) in that the proposal is to create more suitable building lots.

Title: F-CONSISTENT WITH
Wording Consistent with JCC Title 18.35.060.2(a), the proposal will not create an additional lot, tract, or parcel.

Title: F-CONSISTENT WITH
Wording Consistent with JCC Title 18.35.060.2(b), the proposal is not within a binding site plan.

Title: F-CONSISTENT WITH
Wording Consistent with JCC Title 18.35.060.2(c), the proposal will not relocate an entire lot, tract, or parcel.

Title: F-CONSISTENT WITH
Wording Consistent with JCC Title 18.35.060.2(d), the proposal is not inconsistent with the conditions of approval of any restrictions or covenants.

Title: F-PUBLIC WATER - SIPZ N/A
Wording The parcels will be served by a public water system (Quimper) and therefore SIPZ conditions will not apply.

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on February 6, 2006 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Coastal Seawater Intrusion Protection Zones (SIPZ).

Title: F-SIPZ
Wording Marine shorelines and islands are susceptible to a condition that is known as seawater intrusion. Seawater intrusion is a condition in which the saltwater/freshwater interface in an aquifer moves inland so that wells drilled on upland areas cannot obtain freshwater suitable for public consumption without significant additional treatment and cost. Maintaining a stable balance in the saltwater/freshwater interface is primarily a function of the rate of aquifer recharge (primarily through rainfall) and the rate of groundwater withdrawals (primarily through wells). The Washington Department of Ecology is the agency with statutory authority to regulate groundwater withdrawal for individual wells in Jefferson County. New development, redevelopment, and land use activities on islands and in close proximity to marine shorelines in particular should be developed in such a manner to maximize aquifer recharge and maintain the saltwater/freshwater balance to the maximum extent possible by infiltrating stormwater runoff so that it recharges the aquifer.

Title: F-Coastal SIPZ
Wording The parcel is located within a coastal SIPZ (seawater intrusion protection zone) according to the County GIS map. There are voluntary and mandatory measures identified in the Jefferson County Seawater Intrusion Policy (Resolution 44-22, effective September 23, 2002) that apply to well drilling proposals and building permit applications on existing lots of record. A Coastal SIPZ is defined as: all islands and area within one-quarter mile of marine shoreline, but no history of chloride concentration above 100 mg/L in groundwater sources within 1000 feet.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(2)(j).

Title: F-APPROVAL FOR BLA ONLY
Wording This approval is for a Boundary Line Adjustment only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.