Permit Case Summary

Case Number: Search Help

Case Number:SEP2021-00055 Case Status:Finaled Date Received:4/6/2021
Description: Date Issued:6/15/2021
Applicant: STO LLC Expiration Date:6/15/2024 12:00:00 AM
Site Address:116 SUNSET MEADOWS LN Case Finaled:10/10/2022
Parcel No:971900010 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 10/10/2022
Disposition: DONE
Description: INSTALLATION- TANKS PUD SYSTEM
Date Completed: 7/15/2022
Disposition: DONE
Description: Issue permit (Fm) "A"
Date Completed: 6/15/2021
Disposition: DONE
Description: Pending letter; add inf (Fm)
Date Completed: 6/15/2021
Disposition: DONE
Description: Septic Permit Application (Fm)
Date Completed: 4/6/2021
Disposition: DONE
Description: Monitoring Agreemt Sent (Fm)
Date Completed: 4/6/2021
Disposition: DONE
Description: Asbuilt drawing submitted
Date Completed: 10/11/2022
Disposition: DONE
Description: Initial Site Inspection by HD
Date Completed: 5/10/2021
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 6/11/2021
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 6/10/2021
Disposition: DONE
Description: Case Entered "P"
Date Completed: 4/8/2021
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: ONGOING MONITORING
Wording H - AS PER WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 ALL ONSITE SEWAGE SYSTEMS REQUIRE THAT A RESTRICTIVE COVENANT REGARDING THE MONITORING OF THE ONSITE SEPTIC SYSTEM BE RECORDED TO THE PROPERTY TITLE. THE PROPERTY OWNER SHALL ASSURE THAT MONITORING IS PROVIDED BY AN APPROVED ENTITY AT THE FREQUENCY DEFINED PER STATE WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED. A COPY OF THE RECORDED OPERATIONS AND MONITORING AGREEMENT IS REQUIRED PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL PERMIT

Title: alternative-asbuilt required
Wording H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from septic tank and drainfield area.

Title: community df-tanks only
Wording Installer will verify with the system manager, the Jefferson County PUD #1, and the designer for specification requirements and inspections required by either party.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: System Capacity-no ADU
Wording This system as designed and approved is sized for only one single family residence. It is not sized for an Accessory Dwelling Unit (ADU). The minimum daily design flow per residence is 240 GPD.

Title: Water line setback
Wording 10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.

Title: SCREEN REQUIRED
Wording A screen shall be provided at the outlet of the septic tank

Title: O & M Manual required
Wording Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.

Title: O & M Manual required
Wording Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.

Title: Designer Notification/inspections
Wording Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.

Title: Installation Inspection
Wording Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.

Title: No Building Permit Guaranteed
Wording Approval/issuance of a sewage disposal permit or installation of a septic system does not guarantee the approval of other development or a building permit on this site. Future buildings that require connection to an on-site sewage system (OSS) shall only be approved if the OSS meets the current standards and codes in effect at the time of the building application.

Title: Code Compliance
Wording All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.

Title: PUD Notification of Installation
Wording At the time of installation, the PUD must be notified by the Designer when tank(s) are installed.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) for the control of stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: Connection to Public Water
Wording This approval is valid only with a connection to an approved public water supply.