Case Number:SEP2020-00054 Case Status:Approved Date Received:3/25/2020
Description:Lot # 6. Connected to SEP96-00338 (community drainfield) Date Issued:4/15/2020
Applicant: STO LLC Expiration Date:4/15/2023 12:00:00 AM
Site Address:74 SUNSET MEADOWS LN Case Finaled:
Parcel No:971900006 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Issue permit (Fm) "A"
Date Completed: 4/15/2020
Disposition: DONE
Description: Septic Permit Application (Fm)
Date Completed: 3/26/2020
Disposition: DONE
Description: Monitoring Agreemt Sent (Fm)
Date Completed: 3/12/2020
Disposition: DONE
Description: Asbuilt drawing submitted
Date Completed:
Disposition:
Description: Initial Site Inspection by HD
Date Completed: 4/15/2020
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 4/15/2020
Disposition: DONE
Description: Case Entered "P"
Date Completed: 3/26/2020
Disposition:
Description: Stormwater Review-U
Date Completed: 4/15/2020
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: ONGOING MONITORING
Wording H - AS PER WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 ALL ONSITE SEWAGE SYSTEMS REQUIRE THAT A RESTRICTIVE COVENANT REGARDING THE MONITORING OF THE ONSITE SEPTIC SYSTEM BE RECORDED TO THE PROPERTY TITLE. THE PROPERTY OWNER SHALL ASSURE THAT MONITORING IS PROVIDED BY AN APPROVED ENTITY AT THE FREQUENCY DEFINED PER STATE WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED. A COPY OF THE RECORDED OPERATIONS AND MONITORING AGREEMENT IS REQUIRED PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL PERMIT

Title: protection from vehicular traffic
Wording All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from septic tank and drainfield area.

Title: transport line double cased
Wording Any portion of transport line under a driven way is to be sleeved/cased or equivalent.

Title: comm- sep tank inspection
Wording Health Department is to be contacted for a final inspection of the septic tank and pump chamber prior to covering.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: risers
Wording Risers are required to grade with secured lids over both compartments and over the outlet of the septic tank for inspection and maintenance/monitoring. Minimum 20" riser over inlet.

Title: conventional-asbuilt required
Wording H - An asbuilt drawing and certification of completion by the Designer is required prior to final approval.

Title: Water line setback
Wording 10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.

Title: O & M Manual required
Wording Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.

Title: Designer Notification/inspections
Wording Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.

Title: Customer Agreement- Comm Sys
Wording H- A signed Customer Agreement with the system owner, Jefferson County PUD #1, shall be submitted to this office prior to final approval of the septic permit. Contact the PUD at 360-385-5800.

Title: Installation Inspection
Wording Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.

Title: No Building Permit Guaranteed
Wording Approval/issuance of a sewage disposal permit or installation of a septic system does not guarantee the approval of other development or a building permit on this site. Future buildings that require connection to an on-site sewage system (OSS) shall only be approved if the OSS meets the current standards and codes in effect at the time of the building application.

Title: Code Compliance
Wording All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.

Title: PUD Notification of Installation
Wording At the time of installation, the PUD must be notified by the Designer when tank(s) are installed.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) for the control of stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.