Permit Case Summary

Case Number: Search Help

Case Number:SEP2019-00077 Case Status:Finaled Date Received:4/3/2019
Description:Lot #37, to be connected to SEP96-00340. Date Issued:6/1/2019
Applicant: STO LLC Expiration Date:6/1/2022 12:00:00 AM
Site Address:144 SUNSET MEADOWS LN Case Finaled:4/14/2020
Parcel No:971900037 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 4/14/2020
Disposition: DONE
Description: Monitoring Agreemt Sent (Fm)
Date Completed: 12/31/2019
Disposition: DONE
Description: INSTALLATION START NOTICE
Date Completed: 11/22/2019
Disposition: DONE
Description: Issue permit (Fm) "A"
Date Completed: 6/1/2019
Disposition: DONE
Description: Septic Permit Application (Fm)
Date Completed: 4/11/2019
Disposition: DONE
Description: Asbuilt drawing submitted
Date Completed: 4/14/2020
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 4/19/2019
Disposition: DONE
Description: Initial Site Inspection by HD
Date Completed: 5/30/2019
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 6/1/2019
Disposition: DONE
Description: Case Entered "P"
Date Completed: 4/8/2019
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: ONGOING MONITORING
Wording H - AS PER WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 ALL ONSITE SEWAGE SYSTEMS REQUIRE THAT A RESTRICTIVE COVENANT REGARDING THE MONITORING OF THE ONSITE SEPTIC SYSTEM BE RECORDED TO THE PROPERTY TITLE. THE PROPERTY OWNER SHALL ASSURE THAT MONITORING IS PROVIDED BY AN APPROVED ENTITY AT THE FREQUENCY DEFINED PER STATE WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED. A COPY OF THE RECORDED OPERATIONS AND MONITORING AGREEMENT IS REQUIRED PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL PERMIT

Title: pressure test observation
Wording Health Dept. required to observe pressure test to confirm connection to and settings of the community system under SEP96-00340 with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.

Title: alternative-asbuilt required
Wording H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from septic tank area.

Title: community df-tanks only
Wording Installer will verify with the system manager, the Jefferson County PUD #1, and the designer for specifications of pump requirements and inspections required by either party.

Title: comm- sep tank inspection
Wording Health Department is to be contacted for a final inspection of the septic tank prior to covering.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: domestic strength waste
Wording This onsite sewage system is designed for domestic strength wastewater only. Disposal of any other waste strength is considered a violation of this permit.

Title: risers
Wording Risers are required to grade with secured lids over both compartments and over the outlet of the septic tank for inspection and maintenance/monitoring. Minimum 20" riser over inlet.

Title: Water line setback
Wording 10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.

Title: O & M Manual required
Wording Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.

Title: System capacity/uses
Wording Approval of this permit does not assure the existing septic system has capacity for all uses allowed by current code.

Title: Designer Notification/inspections
Wording Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.

Title: Customer Agreement- Comm Sys
Wording H- A signed Customer Agreement with the system owner, shall be submitted to this office prior to final approval of the septic permit.

Title: Installation Inspection
Wording Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.

Title: Certified Installer Required
Wording This system must be constructed by an installer certified by the Jefferson County Public Health Department per Jefferson County Code 8.15.120 (9) and state code WAC246-272A-0250.

Title: Code Compliance
Wording All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.

Title: PUD Notification of Installation
Wording At the time of installation, the PUD must be notified by the Designer when tank(s) are installed.

Title: TANK OUTLET ELEVATION-NO HOLD
Wording Septic tank outlet shall be installed to enable connection to the existing stubout on the lot in order to assure fall to the existing tank to community drainfield.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on April 12, 2019 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review, the following ESAs were confirmed to be present on the subject property: critical aquifer recharge area

Title: RES COV-IRONDALE SAN SEWER
Wording A Restrictive Covenant for Irondale/Hadlock Sanitary Sewer System No Protest Agreement was recorded under AFN 538595 with the Jefferson County Auditor.