Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
11/25/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Monitoring Agreemt Sent (Fm)
|
|
Date Completed:
|
| | |
11/25/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
INSTALLATION START NOTICE
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue permit (Fm) "A"
|
|
Date Completed:
|
| | |
10/26/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (Fm)
|
|
Date Completed:
|
| | |
8/29/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pressure test required
|
|
Date Completed:
|
| | |
11/22/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Asbuilt drawing submitted
|
|
Date Completed:
|
| | |
11/18/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection by HD
|
|
Date Completed:
|
| | |
10/22/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
10/10/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
10/22/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered "P"
|
|
Date Completed:
|
| | |
8/28/2018
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
ONGOING MONITORING
|
|
Wording
|
| | |
H - AS PER WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 ALL ONSITE SEWAGE SYSTEMS REQUIRE THAT A RESTRICTIVE COVENANT REGARDING THE MONITORING OF THE ONSITE SEPTIC SYSTEM BE RECORDED TO THE PROPERTY TITLE. THE PROPERTY OWNER SHALL ASSURE THAT MONITORING IS PROVIDED BY AN APPROVED ENTITY AT THE FREQUENCY DEFINED PER STATE WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED.
A COPY OF THE RECORDED OPERATIONS AND MONITORING AGREEMENT IS REQUIRED PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL PERMIT
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.
|
|
|
Title:
|
| | |
alternative-asbuilt required
|
|
Wording
|
| | |
H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
UDC compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.
|
|
|
Title:
|
| | |
O & M Manual required
|
|
Wording
|
| | |
Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.
|
|
|
Title:
|
| | |
Designer Notification/inspections
|
|
Wording
|
| | |
Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.
|
|
|
Title:
|
| | |
Installation Inspection
|
|
Wording
|
| | |
Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.
|
|
|
Title:
|
| | |
No Building Permit Guaranteed
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit or installation of a septic system does not guarantee the approval of other development or a building permit on this site. Future buildings that require connection to an on-site sewage system (OSS) shall only be approved if the OSS meets the current standards and codes in effect at the time of the building application.
|
|
|
Title:
|
| | |
Code Compliance
|
|
Wording
|
| | |
All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|