Permit Case Summary

Case Number: Search Help

Case Number:SEP2017-00239 Case Status:Finaled Date Received:12/26/2017
Description: Date Issued:2/20/2018
Applicant:LINDA J PAUL TRUSTEE Expiration Date:5/20/2018 12:00:00 AM
Site Address:710 RHODODENDRON LN Case Finaled:5/30/2019
Parcel No:988500027 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 5/30/2019
Disposition: DONE
Description: Miscellaneous Action
Date Completed: 5/30/2019
Disposition: DONE
Description: Other req. before final -hold
Date Completed: 5/30/2019
Disposition: DONE
Description: Misc. Conversation or email
Date Completed: 12/5/2018
Disposition: DONE
Description: INSTALLATION START NOTICE
Date Completed: 5/24/2018
Disposition: DONE
Description: Monitoring Agreemt Sent (Fm)
Date Completed: 5/17/2018
Disposition: DONE
Description: Issue permit (Fm) "A"
Date Completed: 2/20/2018
Disposition: DONE
Description: Invoice for DCD Sent
Date Completed: 2/1/2018
Disposition:
Description: DCD Review Time
Date Completed: 2/1/2018
Disposition:
Description: DCD Review Time
Date Completed: 1/31/2018
Disposition:
Description: Up Front Review
Date Completed: 2/1/2018
Disposition: DONE
Description: Septic Permit Application (Fm)
Date Completed: 12/27/2017
Disposition: DONE
Description: Update SOM Repair Recd
Date Completed: 12/28/2017
Disposition: DONE
Description: Pressure test required
Date Completed: 5/24/2018
Disposition: DONE
Description: Asbuilt drawing submitted
Date Completed: 6/18/2018
Disposition: DONE
Description: Initial Site Inspection by HD
Date Completed: 1/26/2018
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 2/16/2018
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 2/20/2018
Disposition: DONE
Description: Case Entered "P"
Date Completed: 12/27/2017
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: ONGOING MONITORING
Wording H - AS PER WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 ALL ONSITE SEWAGE SYSTEMS REQUIRE THAT A RESTRICTIVE COVENANT REGARDING THE MONITORING OF THE ONSITE SEPTIC SYSTEM BE RECORDED TO THE PROPERTY TITLE. THE PROPERTY OWNER SHALL ASSURE THAT MONITORING IS PROVIDED BY AN APPROVED ENTITY AT THE FREQUENCY DEFINED PER STATE WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED. A COPY OF THE RECORDED OPERATIONS AND MONITORING AGREEMENT IS REQUIRED PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL PERMIT

Title: pressure test observation
Wording Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.

Title: alternative-asbuilt required
Wording H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.

Title: Tank Abandonment
Wording H - Existing tank shall be properly abandoned. It shall be pumped and filled with clean fill. Documentation to be provided to Health Dept. prior to final.

Title: protection from vehicular traffic
Wording All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.

Title: dose counter & ETM
Wording Dose counter and elapsed time meter are required in the control panel for all system components.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from septic tank and drainfield area.

Title: water tight tank
Wording Septic tank and pump chamber to be water tight. Extra protection (i.e. Bentonite) to be used around inlet, outlet, and risers due to high water table.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: risers
Wording Risers are required to grade with secured lids over both compartments and over the outlet of the septic tank for inspection and maintenance/monitoring. Minimum 20" riser over inlet.

Title: ATU maintenance
Wording A maintenance and management contract is required with the manufacturers authorized representative. Maintenance of the system shall be completed by a manufacturers authorized representative at the frequency required by the manufacturer.

Title: ATU RECORDING/COMPLIANCE
Wording H - The signed Notice for Maintenance and Monitoring of an Onsite Sewage System shall be recorded to the property title prior to final approval. Non-compliance with the contract or maintenance requirements is a violation of this permit.

Title: surface water setback
Wording Setback to surface waters- 100' required from drainfield and reserve areas. 50' required from tanks.

Title: protective barriers
Wording H - Permanent barriers are required along/around primarydrainfield areas to protect from parking, driving, and other land disturbing activities prior to final.

Title: System Capacity-no ADU
Wording This system as designed and approved is sized for only one single family residence. It is not sized for an Accessory Dwelling Unit (ADU). The minimum daily design flow per residence is 240 GPD.

Title: Water line setback
Wording 10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components. Water line and water meter to be relocated to provide a minimum of 10' setback to all onsite sewage components.

Title: Setback - Drains
Wording A 30' setback shall be maintained from the disposal component and reserve area to any downslope footing, curtain or interceptor drain or drainage ditch.

Title: VIOLATION-limited permit life
Wording This permit was issued to correct a violation of WAC 246-272A. The permit must be completed within 90 days of the date of issuance.

Title: SCREEN REQUIRED
Wording A screen or pump shroud shall be provided around the pump prior to discharge to the drainfield/coils.

Title: O & M Manual required
Wording Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.

Title: Designer Notification/inspections
Wording Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.

Title: Installation Inspection
Wording Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.

Title: Certified Installer Required
Wording This system must be constructed by an installer certified by the Jefferson County Public Health Department per Jefferson County Code 8.15.120 (9) and state code WAC246-272A-0250.

Title: No Building Permit Guaranteed
Wording Approval/issuance of a sewage disposal permit or installation of a septic system does not guarantee the approval of other development or a building permit on this site. Future buildings that require connection to an on-site sewage system (OSS) shall only be approved if the OSS meets the current standards and codes in effect at the time of the building application.

Title: Code Compliance
Wording All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.

Title: GARAGE PLUMBING-HOLD
Wording H - The garage contains a washing machine. No additional plumbing is approved. Additional review and permitting is required if additional plumbing is proposed. Verification of existing plumbing is required prior to final.

Title: APPROVED INSTALLER-HOLD
Wording H - The installer shall be approved by the manufacturer for installation of this proprietary system.

Title: CONFIRMED ESA'S
Wording The application was reviewed by the Jefferson County Department of Community Development Staff on January 23, 2018 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review the following ESAs were confirmed to be present on the subject property: marine nearshore fish and wildlife habitat conservation area, coastal saltwater intrusion protection zone.

Title: SHORELINE EXEMPTION
Wording This project was reviewed and approved as a Shoreline Exemption under JCC 18.25.560(2).

Title: SITE PLAN CHANGES
Wording The site plan submitted with the new septic system application on December 26, 2017 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the approved site plan shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: SEPTIC CODE INTERPRETATION
Wording This proposal is consistent with the Jefferson County Code Interpretation date August 29, 2014 for repair and maintenance of legal nonconforming onsite sewage systems. The proposed repair to the septic tank and drainfield is exempt from critical area review under JCC 18.22.070(6) and (21).

Title: APPROVAL FOR SEPTIC REPAIR ONLY
Wording This approval is for a septic system repair only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed upon future permits.

Title: NO SHOOTING AREA
Wording This parcel is within Brinnon - Black Point no shooting area per JCC 8.50.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.