Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
8/14/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
INSTALLATION START NOTICE
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Monitoring Agreemt Sent (Fm)
|
|
Date Completed:
|
| | |
6/21/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
INSTALLATION START NOTICE
|
|
Date Completed:
|
| | |
6/4/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue permit (Fm) "A"
|
|
Date Completed:
|
| | |
1/19/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DCD Review Time
|
|
Date Completed:
|
| | |
12/18/2017
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Invoice for DCD Sent
|
|
Date Completed:
|
| | |
12/18/2017
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Up Front Review
|
|
Date Completed:
|
| | |
1/4/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pending letter; add inf (Fm)
|
|
Date Completed:
|
| | |
1/19/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (Fm)
|
|
Date Completed:
|
| | |
11/1/2017
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Update SOM Repair Recd
|
|
Date Completed:
|
| | |
11/1/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pressure test required
|
|
Date Completed:
|
| | |
8/13/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Asbuilt drawing submitted
|
|
Date Completed:
|
| | |
7/30/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection by HD
|
|
Date Completed:
|
| | |
11/14/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
12/18/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
1/19/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered "P"
|
|
Date Completed:
|
| | |
11/1/2017
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
ONGOING MONITORING
|
|
Wording
|
| | |
H - AS PER WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 ALL ONSITE SEWAGE SYSTEMS REQUIRE THAT A RESTRICTIVE COVENANT REGARDING THE MONITORING OF THE ONSITE SEPTIC SYSTEM BE RECORDED TO THE PROPERTY TITLE. THE PROPERTY OWNER SHALL ASSURE THAT MONITORING IS PROVIDED BY AN APPROVED ENTITY AT THE FREQUENCY DEFINED PER STATE WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED.
A COPY OF THE RECORDED OPERATIONS AND MONITORING AGREEMENT IS REQUIRED PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL PERMIT
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.
|
|
|
Title:
|
| | |
alternative-asbuilt required
|
|
Wording
|
| | |
H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.
|
|
|
Title:
|
| | |
well setback requirement
|
|
Wording
|
| | |
Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.
|
|
|
Title:
|
| | |
dry season installation
|
|
Wording
|
| | |
Dry season installation required.
|
|
|
Title:
|
| | |
reserve area, alternative
|
|
Wording
|
| | |
When/if designated reserve area is utilized an alternative system providing an additional level of treatment may be required and must comply with code at the time of application for use.
|
|
|
Title:
|
| | |
Tank Abandonment
|
|
Wording
|
| | |
H - Existing tank shall be properly abandoned. It shall be pumped and filled with clean fill. Documentation to be provided to Health Dept. prior to final.
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.
|
|
|
Title:
|
| | |
staking of drainfield
|
|
Wording
|
| | |
Contact designer prior to installation for staking of drainfield area.
|
|
|
Title:
|
| | |
dose counter & ETM
|
|
Wording
|
| | |
Dose counter and elapsed time meter are required in the control panel for all system components.
|
|
|
Title:
|
| | |
transport line double cased
|
|
Wording
|
| | |
Any portion of transport line under a driven way is to be sleeved/cased or equivalent.
|
|
|
Title:
|
| | |
water tight tank
|
|
Wording
|
| | |
Septic tank and pump chamber to be water tight. Extra protection (i.e. Bentonite) to be used around inlet, outlet, and risers due to high water table.
|
|
|
Title:
|
| | |
risers
|
|
Wording
|
| | |
Risers are required to grade with secured lids over both compartments and over the outlet of the septic tank for inspection and maintenance/monitoring. Minimum 20" riser over inlet.
|
|
|
Title:
|
| | |
surface water setback
|
|
Wording
|
| | |
Setback to surface waters- 100' required from drainfield and reserve areas. 50' required from tanks.
|
|
|
Title:
|
| | |
System Capacity-no ADU
|
|
Wording
|
| | |
This system as designed and approved is sized for only one single family residence. It is not sized for an Accessory Dwelling Unit (ADU). The minimum daily design flow per residence is 240 GPD.
|
|
|
Title:
|
| | |
Water line setback
|
|
Wording
|
| | |
10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components, EXCEPT as specifically approved in the plan received 11/1/17.
|
|
|
Title:
|
| | |
Setback - Drains
|
|
Wording
|
| | |
A 30' setback shall be maintained from the disposal component and reserve area to any downslope footing, curtain or interceptor drain or drainage ditch.
|
|
|
Title:
|
| | |
VIOLATION-limited permit life
|
|
Wording
|
| | |
This permit was issued to correct a violation of WAC 246-272A. Per JCC 8.15 the permit must be completed within 90 days of the date of issuance but because of the requirement to install during the dry season based on soil conditions the permit is being issued for 180 days, 6 months.
|
|
|
Title:
|
| | |
SCREEN REQUIRED
|
|
Wording
|
| | |
A screen shall be provided either at the outlet of the septic tank or around the pump or at both locations. A pump shroud is required if only an outlet baffle filter is used.
|
|
|
Title:
|
| | |
O & M Manual required
|
|
Wording
|
| | |
Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.
|
|
|
Title:
|
| | |
Designer Notification/inspections
|
|
Wording
|
| | |
Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.
|
|
|
Title:
|
| | |
Installation Inspection
|
|
Wording
|
| | |
Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.
|
|
|
Title:
|
| | |
Certified Installer Required
|
|
Wording
|
| | |
This system must be constructed by an installer certified by the Jefferson County Public Health Department per Jefferson County Code 8.15.120 (9) and state code WAC246-272A-0250.
|
|
|
Title:
|
| | |
No Building Permit Guaranteed
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit or installation of a septic system does not guarantee the approval of other development or a building permit on this site. Future buildings that require connection to an on-site sewage system (OSS) shall only be approved if the OSS meets the current standards and codes in effect at the time of the building application.
|
|
|
Title:
|
| | |
Code Compliance
|
|
Wording
|
| | |
All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.
|
|
|
Title:
|
| | |
SHORELINE EXEMPTION
|
|
Wording
|
| | |
This project was reviewed and approved as a Shoreline Exemption under JCC 18.25.560(2).
|
|
|
Title:
|
| | |
SEPTIC CODE INTERPRETATION
|
|
Wording
|
| | |
This proposal is consistent with the Jefferson County Code Interpretation dated August 29, 2014 for repair and maintenance of legal nonconforming onsite sewage systems. The proposed repair to the septic tank and drainfield is exempt from critical area review under JCC 18.22.070(6) and (21).
|
|
|
Title:
|
| | |
CONFIRMED ESA'S
|
|
Wording
|
| | |
The application was reviewed by Jefferson County staff for the potential presence of critical areas under the provisions of the Unified Development Code (UDC). After a Geographic Information Systems mapping review the following critical areas were confirmed to be present on the subject property: marine nearshore fish and wildlife habitat conservation area, SARPA critical aquifier recharge area, coastal saltwater intrusion protection zone.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the septic repair application on November 1, 2017 has been reviewed for consitency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the approved site plan shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
SEPTIC RESERVE AREA
|
|
Wording
|
| | |
The reserve area is proposed in shoreline jurisdiction. As no development is proposed at this time in the reserve area location, the impacts to critical areas has not been reviewed. A variance, buffer reduction or habitat management plan may be required at time of septic permit application for septic components within this reserve area location. The septic application shall comply with all shoreline and critical area regulations at time of permit application.
|
|
|
Title:
|
| | |
APPROVAL FOR SEPTIC REPAIR ONLY
|
|
Wording
|
| | |
This approval is for a septic system repair only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed upon future permits.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|