Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
5/31/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
INSTALLATION START NOTICE
|
|
Date Completed:
|
| | |
4/11/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Monitoring Agreemt Sent (Fm)
|
|
Date Completed:
|
| | |
2/15/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
INSTALLATION START NOTICE
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue permit (Fm) "A"
|
|
Date Completed:
|
| | |
12/7/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Miscellaneous Action
|
|
Date Completed:
|
| | |
12/5/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pending letter; add inf (Fm)
|
|
Date Completed:
|
| | |
12/7/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (Fm)
|
|
Date Completed:
|
| | |
9/8/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pressure test required
|
|
Date Completed:
|
| | |
4/11/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Asbuilt drawing submitted
|
|
Date Completed:
|
| | |
5/31/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection by HD
|
|
Date Completed:
|
| | |
9/28/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/27/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/27/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered "P"
|
|
Date Completed:
|
| | |
9/8/2017
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.
|
|
|
Title:
|
| | |
alternative-asbuilt required
|
|
Wording
|
| | |
H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.
|
|
|
Title:
|
| | |
other setbacks req.
|
|
Wording
|
| | |
Drainfield and reserve must maintain a 10' min setback from the proposed foundation per BLD17-00493
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
transport line double cased
|
|
Wording
|
| | |
Any portion of transport line under a driven way is to be sleeved/cased or equivalent.
|
|
|
Title:
|
| | |
protective barriers
|
|
Wording
|
| | |
H - Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.
|
|
|
Title:
|
| | |
Water line setback
|
|
Wording
|
| | |
10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.
|
|
|
Title:
|
| | |
O & M Manual required
|
|
Wording
|
| | |
Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.
|
|
|
Title:
|
| | |
Designer Notification/inspections
|
|
Wording
|
| | |
Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.
|
|
|
Title:
|
| | |
Installation Inspection
|
|
Wording
|
| | |
Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.
|
|
|
Title:
|
| | |
Code Compliance
|
|
Wording
|
| | |
All construction and development activities must comply with all permit conditions, Washington State and Jefferson County Codes and Recommended Standards and Guidance documents in effect when the permit is issued.
|
|
|
Title:
|
| | |
DESCRIPTION OF PLAN
|
|
Wording
|
| | |
This permit is to expand SEP15-00033 (360 gpd system finaled in 2/17/16) to provide a capacity of 480gpd by adding one 50' lateral to the existing system and modifiing the pump and manifold. This permit is in association with BLD17-00493. See BLD permit application for site plan provided for the new 2 bedroom ADU to be added to the property. This system will serve the primary residence and proposed ADU for a total capacity of 480 gpd.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|