Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
2/16/2011
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
3/29/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
INSTALLATION START NOTICE
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Monitoring Agreemt Sent (Fm)
|
|
Date Completed:
|
| | |
11/2/2009
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
INSTALLATION START NOTICE
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
8/12/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pending letter; add inf (F)
|
|
Date Completed:
|
| | |
7/18/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print ESA Review Form-F
|
|
Date Completed:
|
| | |
3/17/2008
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
3/17/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
3/17/2008
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
7/15/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
7/15/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection by HD
|
|
Date Completed:
|
| | |
4/2/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Asbuilt drawing submitted
|
|
Date Completed:
|
| | |
3/24/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pressure test required
|
|
Date Completed:
|
| | |
3/3/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
ONGOING MONITORING
|
|
Wording
|
| | |
H - AS PER WAC 246-272A AND JEFFERSON COUNTY CODE 8.15 ALL SYSTEMS REQUIRE MONITORING. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING AGREEMENT RECORDED TO THE PROPERTY TITLE PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM.
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.
|
|
|
Title:
|
| | |
alternative-asbuilt required
|
|
Wording
|
| | |
H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.
|
|
|
Title:
|
| | |
well setback requirement
|
|
Wording
|
| | |
Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.
|
|
|
Title:
|
| | |
dry season installation
|
|
Wording
|
| | |
Dry season installation required.
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.
|
|
|
Title:
|
| | |
installed on natural contours
|
|
Wording
|
| | |
Drainlines are to be installed along the natural contours.
|
|
|
Title:
|
| | |
staking of drainfield
|
|
Wording
|
| | |
Contact designer prior to installation for staking of drainfield area.
|
|
|
Title:
|
| | |
dose counter & ETM
|
|
Wording
|
| | |
Dose counter and elapsed time meter are required in the control panel for all system components.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
water tight tank
|
|
Wording
|
| | |
Septic tank and pump chamber to be water tight. Extra protection (i.e. Bentonite) to be used around inlet, outlet, and risers due to high water table.
|
|
|
Title:
|
| | |
no building permit guarantee
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.
|
|
|
Title:
|
| | |
UDC compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.
|
|
|
Title:
|
| | |
MONITORING SCHEDULE
|
|
Wording
|
| | |
As per Jefferson County Code 8.15 all onsite sewage systems require monitoring. Monitoring shall be provided by an approved entity. THIS SYSTEM IS REQUIRED TO BE INSPECTED PER JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED.
|
|
|
Title:
|
| | |
surface water setback
|
|
Wording
|
| | |
Setback to surface waters- 100' required from drainfield and reserve areas. 50' required from tanks.
|
|
|
Title:
|
| | |
protective barriers
|
|
Wording
|
| | |
H - Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.
|
|
|
Title:
|
| | |
Water line setback
|
|
Wording
|
| | |
10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.
|
|
|
Title:
|
| | |
Setback - Drains
|
|
Wording
|
| | |
A 30' setback shall be maintained from the disposal component and reserve area to any downslope footing, curtain or interceptor drain or drainage ditch.
|
|
|
Title:
|
| | |
O & M Manual required
|
|
Wording
|
| | |
Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.
|
|
|
Title:
|
| | |
Designer Notification/inspections
|
|
Wording
|
| | |
Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.
|
|
|
Title:
|
| | |
Installation Inspection
|
|
Wording
|
| | |
Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|