Permit Case Summary

Case Number: Search Help

Case Number:SEP2007-00337 Case Status:Finaled Date Received:10/8/2007
Description:drainfield and tanks on 942902414 to serve commercial business on 942903401 SEP84-00085 is filed with this permit. Date Issued:11/6/2007
Applicant:LAWRENCE JOHNSON Expiration Date:11/6/2010 12:00:00 AM
Site Address:10733 RHODY DR Case Finaled:4/21/2008
Parcel No:942903414 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 4/21/2008
Disposition: DONE
Description: INSTALLATION START NOTICE
Date Completed:
Disposition:
Description: Monitoring Agreement Sent
Date Completed: 2/12/2008
Disposition: DONE
Description: INSTALLATION START NOTICE
Date Completed:
Disposition:
Description: Issue permit (F)
Date Completed: 11/6/2007
Disposition: DONE
Description: Print ESA Review Form-F
Date Completed: 10/8/2007
Disposition:
Description: Septic Permit Application (F)
Date Completed: 10/8/2007
Disposition: DONE
Description: Case Entered
Date Completed: 10/8/2007
Disposition:
Description: Stormwater Review-U
Date Completed: 11/6/2007
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 11/6/2007
Disposition: DONE
Description: Initial Site Inspection by HD
Date Completed: 11/1/2007
Disposition: DONE
Description: Asbuilt drawing submitted
Date Completed: 4/21/2008
Disposition: DONE
Description: Pressure test required
Date Completed: 2/20/2008
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: ONGOING MONITORING
Wording H - AS PER WAC 246-272 AND JEFFERSON COUNTY CODE 8.15 ALL SYSTEMS REQUIRE MONITORING. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING AGREEMENT RECORDED TO THE PROPERTY TITLE PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM.

Title: pressure test observation
Wording Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.

Title: alternative-asbuilt required
Wording H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.

Title: well setback requirement
Wording Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.

Title: reserve area, alternative
Wording When/if designated reserve area is utilized an alternative system providing an additional level of treatment may be required.

Title: easement
Wording H - Recorded easement required for primary and/or reserve drainfields. Easement recorded 528063 with the Jefferson County Auditors office.

Title: Tank Abandonment
Wording H - Existing tank shall be properly abandoned. It shall be pumped and filled with clean fill. Documentation to be provided to Health Dept. prior to final.

Title: protection from vehicular traffic
Wording All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.

Title: installed on natural contours
Wording Drainlines are to be installed along the natural contours.

Title: staking of drainfield
Wording Contact designer prior to installation for staking of drainfield area.

Title: dose counter & ETM
Wording Dose counter and elapsed time meter are required in the control panel for all system components.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from septic tank and drainfield area.

Title: transport line double cased
Wording Any portion of transport line under a driven way is to be sleeved/cased or equivalent or installed per design specifications.

Title: no building permit guarantee
Wording Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.

Title: SAND LINED TRENCH/BED
Wording TRENCH TO BE EXCAVATED AND THEN BACKFILLED WITH ASTM 33 TYPE SAND TO 24" AND UP SIDE WALLS AS PER DESIGN.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: domestic strength waste
Wording This onsite sewage system is designed for domestic strength wastewater only. Disposal of any other waste strength is considered a violation of this permit.

Title: risers
Wording Risers are required to grade with secured lids over both compartments and over the outlet of the septic tank for inspection and maintenance/monitoring. Minimum 20" riser over inlet.

Title: MONITORING SCHEDULE
Wording As per Jefferson County Code 8.15 all onsite sewage systems require monitoring. Monitoring shall be provided by an approved entity. THIS SYSTEM IS REQUIRED TO BE INSPECTED PER JEFFERSON COUNTY CODE 8.15 AS ADOPTED OR AMENDED.

Title: surface water setback
Wording Setback to surface waters- 100' required from drainfield and reserve areas. 50' required from tanks.

Title: protective barriers
Wording H - Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.

Title: System Capacity-no ADU
Wording This system as designed and approved is sized for only one single family residence. It is not sized for an Accessory Dwelling Unit (ADU). The minimum daily design flow per residence is 240 GPD.

Title: Water line setback
Wording 10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.

Title: Setback - Drains
Wording A 30' setback shall be maintained from the disposal component and reserve area to any downslope footing, curtain or interceptor drain or drainage ditch.

Title: PUMP CHAMBER
Wording Pump chamber shall be water tight and a minimum capacity of 1,000 gallons. It shall be equipped with a control panel outside within line of sight of the pump chamber. The panel shall have an audio and visual alarm, a cycle counter and a riser to grade. It shall be UL listed and meet L&I requirements.

Title: SCREEN REQUIRED
Wording A screen shall be provided either at the outlet of the septic tank or around the pump or at both locations. A pump shroud is required if only an outlet baffle filter is used.

Title: O & M Manual required
Wording Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner and the Health Department. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.

Title: Designer Notification/inspections
Wording Designer must be contacted prior to start of construction and for inspections during installation. DESIGNER IS REQUIRED TO DO A PRECOVER INSPECTION ON ALL TYPES OF SYSTEMS.

Title: Installation Inspection
Wording Notification of the start of construction shall be faxed or emailed to Jefferson County Public Health ONE WORKING DAY prior to start.

Title: CUSTOM CONDITION-NO HOLD
Wording ALL CONSTRUCTION AND DEVELOPMENT ACTIVITIES MUST COMPLY WITH ALL PERMIT CONDITIONS, STATE AND LOCAL CODES, AND RECOMMENDED STANDARDS AND GUIDANCE DOCUMENTS IN EFFECT WHEN THE PERMIT IS ISSUED.

Title: CUSTOM CONDITION-HOLD
Wording H - the installation of the transport lines to the septic tank and pump chamber must be installed in accordance with the design specifications and must be documented as such on the construction drawings by the septic system designer.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.