Description:
|
| | |
Miscellaneous Action
|
|
Date Completed:
|
| | |
7/5/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
12/19/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
INSTALLATION START NOTICE
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Monitoring Agreement Sent
|
|
Date Completed:
|
| | |
11/29/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
7/16/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pending letter; add inf (F)
|
|
Date Completed:
|
| | |
7/16/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
5/13/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print ESA Review Form-F
|
|
Date Completed:
|
| | |
5/18/2007
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
5/18/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
5/18/2007
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
5/3/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
5/3/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection by HD
|
|
Date Completed:
|
| | |
5/22/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Asbuilt drawing submitted
|
|
Date Completed:
|
| | |
12/19/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pressure test required
|
|
Date Completed:
|
| | |
12/11/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
pud monitoring
|
|
Wording
|
| | |
H - AS PER WAC 246-272 AND JEFFERSON COUNTY CODE 8.15 ALL SYSTEMS REQUIRE MONITORING. THIS MONITORING IS PROVIDED BY AGREEMENT BETWEEN THE JEFFERSON COUNTY ENVIRONMENTAL HEALTH DIVISION AND THE JEFFERSON COUNTY PUBLIC UTILITY DISTRICT #1. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING CONTRACT WITH THE PUD #1 PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM.
While the County strongly recommends that the property owner allow inspectors to enter their property to inspect the system in order to insure that the system is functioning correctly, the property owner always has the right under the Fourth Amendment and our State Constitution, to refuse the inspectors access to their property. The property owner never loses the right to refuse access and can do so despite never having refused access before.
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test with system designer when system fully installed/complete, 48 hours notice to be provided for scheduling.
|
|
|
Title:
|
| | |
alternative-asbuilt required
|
|
Wording
|
| | |
H - An asbuilt drawing and certification of completion by the designer is required prior to final approval.
|
|
|
Title:
|
| | |
well setback requirement
|
|
Wording
|
| | |
Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.
|
|
|
Title:
|
| | |
reserve area, alternative
|
|
Wording
|
| | |
When/if designated reserve area is utilized an alternative system providing an additional level of treatment may be required.
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.
|
|
|
Title:
|
| | |
installed on natural contours
|
|
Wording
|
| | |
Drainlines are to be installed along the natural contours.
|
|
|
Title:
|
| | |
staking of drainfield
|
|
Wording
|
| | |
Contact designer prior to installation for staking of drainfield area.
|
|
|
Title:
|
| | |
dose counter
|
|
Wording
|
| | |
Dose counters are required in the control panel for all drainfield components.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
transport line double cased
|
|
Wording
|
| | |
Any portion of transport line under a driven way is to be sleeved/cased or equivalent.
|
|
|
Title:
|
| | |
no building permit guarantee
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.
|
|
|
Title:
|
| | |
UDC compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.
|
|
|
Title:
|
| | |
state onsite regs waiver
|
|
Wording
|
| | |
This site has been granted a waiver from the state onsite sewage regulation 246-272-09501(1): disposal component down from 30 to 15 feet from a down-gradient drainage ditch. Compliance with conditions of the waiver is required.
|
|
|
Title:
|
| | |
minimum land RESTRICTIVE COV
|
|
Wording
|
| | |
H - This permit is granted based on the recorded RESTRICTIVE COVENANT combining lots 5-9, and 4-10 of block 19, Phillips Bayview Addition to meet the minimum land area required under WAC 246-272 Onsite Sewage Code. COVENANT recorded AFN 523790.
|
|
|
Title:
|
| | |
risers
|
|
Wording
|
| | |
Risers are required to grade with secured lids over both compartments and over the outlet of the septic tank for inspection and maintenance/monitoring. Minimum 20" riser over inlet.
|
|
|
Title:
|
| | |
MONITORING SCHEDULE
|
|
Wording
|
| | |
As per Jefferson County Code 8.15 all onsite sewage systems require monitoring. Monitoring shall be provided by an approved entity. THIS SYSTEM IS REQUIRED TO BE INSPECTED EVERY 3 YEARS AT 6 MONTHS, AT ONE YEAR AND EVERY 3 YEARS THEREAFTER. A TIME OF SALE INSPECTION IS REQUIRED SHOULD THIS SCHEDULE HAVE NOT BEEN KEPT CURRENT.
|
|
|
Title:
|
| | |
surface water setback
|
|
Wording
|
| | |
Setback to surface waters- 100' required from drainfield and reserve areas. 50' required from tanks.
|
|
|
Title:
|
| | |
protective barriers
|
|
Wording
|
| | |
H - Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.
|
|
|
Title:
|
| | |
riser on d-box
|
|
Wording
|
| | |
Distribution boxes shall be fitted with a riser to grade, constructed of durable materials and a secured lid, adequately sized to allow visible inspection of the liquid level in the box.
|
|
|
Title:
|
| | |
Water line setback
|
|
Wording
|
| | |
10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.
|
|
|
Title:
|
| | |
Setback - Drains
|
|
Wording
|
| | |
A 30' setback shall be maintained from the disposal component and reserve area to any downslope footing, curtain or interceptor drain or drainage ditch.
|
|
|
Title:
|
| | |
PUMP CHAMBER
|
|
Wording
|
| | |
Pump chamber shall be water tight and a minimum capacity of 1,000 gallons. It shall be equipped with a control panel outside within line of sight of the pump chamber. The panel shall have an audio and visual alarm, a cycle counter and a riser to grade. It shall be UL listed and meet L&I requirements.
|
|
|
Title:
|
| | |
SCREEN REQUIRED
|
|
Wording
|
| | |
A screen shall be provided either at the outlet of the septic tank or around the pump or at both locations. A pump shroud is required if only an outlet baffle filter is used.
|
|
|
Title:
|
| | |
STORMWATER PLAN REQD
|
|
Wording
|
| | |
Per plat notice- Prior to the commencement of any land disturbing activities and prior to issuance of a building permit, a Small Parcel Erosion and Sediment Control Plan shall be developed and submitted to the DCD for review and approval.
|
|
|
Title:
|
| | |
O & M Manual required
|
|
Wording
|
| | |
Before final approval is given, the designer shall provide an operations and maintenance manual to the property owner. The manual must instruct the owner of the on site sewage system on the ways to properly operate and maintain all components of the system.
|
|
|
Title:
|
| | |
Designer Notification/inspections
|
|
Wording
|
| | |
Designer must be contacted prior to start of construction and for inspections during installation.
|
|
|
Title:
|
| | |
CUSTOM CONDITION-NO HOLD
|
|
Wording
|
| | |
ALL CONSTRUCTION AND DEVELOPMENT ACTIVITIES MUST COMPLY WITH ALL PERMIT CONDITIONS, STATE AND LOCAL CODES, AND RECOMMENDED STANDARDS AND GUIDANCE DOCUMENTS IN EFFECT WHEN THE PERMIT IS ISSUED.
|
|
|
Title:
|
| | |
CUSTOM CONDITION-NO HOLD
|
|
Wording
|
| | |
SHOULD THE STATED COMMERCIAL USE OF THIS BUILDING CHANGE OR THE NUMBER OF EMPLOYEES EXCEED 22, WATER-USE RECORDS AND WASTE-WATER STRENGTH DATA MAY BE REQUESTED AT THE OWNERS EXPENSE.
|
|
|
Title:
|
| | |
CUSTOM CONDITION-HOLD
|
|
Wording
|
| | |
H - All septic connections to this system must be verified for volume based upon system capacity and use prior to final.
|
|
|
Title:
|
| | |
CUSTOM CONDITION-HOLD
|
|
Wording
|
| | |
H - ALL SITE DEVELOPMENT ACTIVITIES MUST NOT ADVERSELY IMPACT OR ENCROACH UPON THE PRIMARY OR RESERVE DRAINFIELD AREAS.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|