Case Number:SEP2005-00304 Case Status:Finaled Date Received:9/14/2005
Description: Date Issued:11/2/2005
Applicant:CAROL FLETCHER Expiration Date:11/2/2008 12:00:00 AM
Site Address:125 LAWN ST Case Finaled:9/21/2006
Parcel No:901024005 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 9/21/2006
Disposition: DONE
Description: Asbuilt drawing submitted
Date Completed: 9/15/2006
Disposition: DONE
Description: Issue permit (F)
Date Completed: 11/2/2005
Disposition: DONE
Description: Print ESA Review Form-F
Date Completed: 9/14/2005
Disposition:
Description: Septic Permit Application (F)
Date Completed: 9/19/2005
Disposition: DONE
Description: Case Entered
Date Completed: 9/14/2005
Disposition:
Description: Stormwater Review-U
Date Completed: 11/2/2005
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 11/2/2005
Disposition: DONE
Description: Initial Site Inspection by HD
Date Completed: 10/18/2005
Disposition: DONE
Description: Pressure test required
Date Completed: 9/14/2006
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: pud monitoring
Wording AS PER WAC 246-272 AND JEFFERSON COUNTY CODE 8.15 ALL SYSTEMS REQUIRE MONITORING. THIS MONITORING IS PROVIDED BY AGREEMENT BETWEEN THE JEFFERSON COUNTY ENVIRONMENTAL HEALTH DIVISION AND THE JEFFERSON COUNTY PUBLIC UTILITY DISTRICT #1. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING CONTRACT WITH THE PUD #1 PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM. While the County strongly recommends that the property owner allow inspectors to enter their property to inspect the system in order to insure that the system is functioning correctly, the property owner always has the right under the Fourth Amendment and our State Constitution, to refuse the inspectors access to their property. The property owner never loses the right to refuse access and can do so despite never having refused access before.

Title: pressure test observation
Wording Health Dept. required to observe pressure test when system fully installed/complete, 48 hours notice to be provided for scheduling.

Title: alternative-asbuilt required
Wording An asbuilt drawing and certification of completion by the designer is required prior to final approval.

Title: well setback requirement
Wording Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.

Title: protection from vehicular traffic
Wording All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.

Title: dose counter
Wording Dose counters are required in the control panel for all drainfield components.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from septic tank and drainfield area.

Title: transport line double cased
Wording Any portion of transport line under a driven way is to be sleeved/cased or equivalent.

Title: no building permit guarantee
Wording Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.

Title: SAND LINED TRENCH/BED
Wording TRENCH TO BE EXCAVATED TO 48" DEPTH AND THEN BACKFILLED WITH ASTM 33 TYPE SAND TO 24" AND UP SIDE WALLS AS PER DESIGN.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: MONITORING SCHEDULE
Wording As per Jefferson County Code 8.15 all onsite sewage systems require monitoring. Monitoring shall be provided by an approved entity. THIS SYSTEM IS REQUIRED TO BE INSPECTED AT 6 MONTHS, AT ONE YEAR AND EVERY 3 YEARS THEREAFTER.

Title: protective barriers
Wording Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.

Title: Water line setback
Wording 10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.

Title: Designer Notification/inspections
Wording Designer must be contacted prior to start of construction and for inspections during installation.

Title: ORIFICE SHIELDS-NO HOLD
Wording If gravel is used in lieu of gravelless chambers then orifice shields are required over all orifices.

Title: HIGH LEVEL ALARM-NO HOLD
Wording High level alarm shall be set to provide a minimum of 75% of daily design flow above the alarm.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County staff for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: critical aquifer recharge area, priority habitat.