Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
12/18/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
4/8/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pending letter; add inf (F)
|
|
Date Completed:
|
| | |
4/8/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
3/17/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print ESA Review Form-F
|
|
Date Completed:
|
| | |
3/17/2004
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
3/17/2004
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
4/8/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
4/8/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection by HD
|
|
Date Completed:
|
| | |
3/4/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
no building permit guarantee
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.
|
|
|
Title:
|
| | |
UDC compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.
|
|
|
Title:
|
| | |
minimum land RESTRICTIVE COV
|
|
Wording
|
| | |
This permit is granted based on the recorded RESTRICTIVE COVENANT combining lots 1-4 of block 11, Harrisburg Addition to meet the minimum land area required under WAC 246-272 Onsite Sewage Code. COVENANT recorded4/5/04, #482923.
|
|
|
Title:
|
| | |
risers
|
|
Wording
|
| | |
Risers are required to grade with secured lids over both compartments and over the outlet of the septic tank for inspection and maintenance/monitoring. Minimum 20" riser over inlet.
|
|
|
Title:
|
| | |
MONITORING SCHEDULE
|
|
Wording
|
| | |
As per Jefferson County Code 8.15 all onsite sewage systems require monitoring. Monitoring shall be provided by an approved entity. THIS SYSTEM IS REQUIRED TO BE INSPECTED EVERY 3 YEARS.
|
|
|
Title:
|
| | |
conventional-asbuilt required
|
|
Wording
|
| | |
An asbuilt drawing and certification of completion by the Designer is required prior to final approval.
|
|
|
Title:
|
| | |
riser on d-box
|
|
Wording
|
| | |
Distribution boxes shall be fitted with a riser to grade, constructed of durable materials and a secured lid, adequately sized to allow visible inspection of the liquid level in the box.
|
|
|
Title:
|
| | |
System Capacity-no ADU
|
|
Wording
|
| | |
This system as designed and approved is sized for only one single family residence. It is not sized for an Accessory Dwelling Unit (ADU). The minimum daily design flow per residence is 240 GPD.
|
|
|
Title:
|
| | |
Water line setback
|
|
Wording
|
| | |
10' separation required between a Water line and all portions of the onsite sewage system; effluent transport line, tanks, treatment and disposal components.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|