Description:
|
| | |
OSS Inspection-1 Year
|
|
Date Completed:
|
| | |
2/18/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
OSS Inspection-1 Year
|
|
Date Completed:
|
| | |
7/17/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
OSS Inspection-6 Months
|
|
Date Completed:
|
| | |
7/12/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
OSS Inspection-6 Months
|
|
Date Completed:
|
| | |
1/13/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
OSS Inspection-6 Months
|
|
Date Completed:
|
| | |
7/14/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
OSS Inspection-6 Months
|
|
Date Completed:
|
| | |
1/26/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
7/27/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
9/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
10/1/2001
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
9/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
9/18/2001
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection by HD
|
|
Date Completed:
|
| | |
9/26/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pressure test required
|
|
Date Completed:
|
| | |
7/1/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
9/18/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print ESA Review Form-F
|
|
Date Completed:
|
| | |
9/18/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
pud monitoring
|
|
Wording
|
| | |
AS PER WAC 246-272 ALL ALTERNATIVE SYSTEMS REQUIRE MONITORING. THIS MONITORING IS PROVIDED BY AGREEMENT BETWEEN THE JEFFERSON COUNTY ENVIRONMENTAL HEALTH DIVISION AND THE JEFFERSON COUNTY PUBLIC UTILITY DISTRICT #1. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING CONTRACT WITH THE PUD #1 PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM.
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test when system fully installed/complete, 48 hours notice to be provided for scheduling.
|
|
|
Title:
|
| | |
alternative-asbuilt required
|
|
Wording
|
| | |
An asbuilt drawing and certification of completion by the designer is required prior to final approval.
|
|
|
Title:
|
| | |
other setbacks req.
|
|
Wording
|
| | |
10' min setback required from ditch upslope of glendon, and from any portion of drainfield to any water line.
|
|
|
Title:
|
| | |
dry season installation
|
|
Wording
|
| | |
Dry season installation required.
|
|
|
Title:
|
| | |
low use water fixures
|
|
Wording
|
| | |
Low use water fixtures required, 1.6 gal. flush toilets and 2.5 gpm shower heads.
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.
|
|
|
Title:
|
| | |
installed on natural contours
|
|
Wording
|
| | |
Drainlines are to be installed along the natural contours.
|
|
|
Title:
|
| | |
staking of drainfield
|
|
Wording
|
| | |
Contact designer prior to installation for staking of drainfield area.
|
|
|
Title:
|
| | |
dose counter
|
|
Wording
|
| | |
Dose counters are required in the control panel for all drainfield components.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
transport line double cased
|
|
Wording
|
| | |
Any portion of transport line under a driven way is to be double cased or equivalent.
|
|
|
Title:
|
| | |
water tight tank
|
|
Wording
|
| | |
Septic tank and pump chamber to be water tight. Extra protection (i.e. Bentonite) to be used around inlet, outlet, and risers due to high water table.
|
|
|
Title:
|
| | |
no building permit guarantee
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.
|
|
|
Title:
|
| | |
UDC compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.
|
|
|
Title:
|
| | |
risers
|
|
Wording
|
| | |
Risers are required to grade with secured lids over the inlet and outlet of the septic tank. Minimum 24" riser over inlet.
|
|
|
Title:
|
| | |
reduced size df
|
|
Wording
|
| | |
Performance monitoring schedule for treatment systems followed by reduced sized drainfield/infiltrative area shall be :1) Two times per year (once every six months) during the first and second year following installation. 2) One time per year beginning with the third year following installation. 3) In response to complaints or problems.
|
|
|
Title:
|
| | |
protective barriers
|
|
Wording
|
| | |
Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.
|
|
|
Title:
|
| | |
CUSTOM CONDITION-NO HOLD
|
|
Wording
|
| | |
Contact health department for inspection of exposed rim of the biofilter prior to covering. Provide 24 hours notice.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|