Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
1/16/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
9/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pending letter; add inf (F)
|
|
Date Completed:
|
| | |
9/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
8/23/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/23/2001
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/27/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection by HD
|
|
Date Completed:
|
| | |
8/28/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print ESA Review Form-F
|
|
Date Completed:
|
| | |
8/23/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
8/23/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
well setback requirement
|
|
Wording
|
| | |
Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.
|
|
|
Title:
|
| | |
other setbacks req.
|
|
Wording
|
| | |
Maintain 10' min. setback from water line to any portion of septic system
|
|
|
Title:
|
| | |
other setbacks req.
|
|
Wording
|
| | |
25 ft. setback from any 100% slope/bank to be maintained with both primary and reserve.
|
|
|
Title:
|
| | |
trench depth
|
|
Wording
|
| | |
MAXIMUM TRENCH DEPTH 30 INCHES
|
|
|
Title:
|
| | |
reserve area, alternative
|
|
Wording
|
| | |
When/if designated reserve area is utilized an alternative system providing an additional level of treatment may be required.
|
|
|
Title:
|
| | |
low use water fixures
|
|
Wording
|
| | |
Low use water fixtures required, 1.6 gal. flush toilets and 2.5 gpm shower heads.
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.
|
|
|
Title:
|
| | |
installed on natural contours
|
|
Wording
|
| | |
Drainlines are to be installed along the natural contours.
|
|
|
Title:
|
| | |
staking of drainfield
|
|
Wording
|
| | |
Contact designer prior to installation for staking of drainfield area.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
transport line double cased
|
|
Wording
|
| | |
Any portion of transport line under a driven way is to be double cased or equivalent.
|
|
|
Title:
|
| | |
UDC compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.
|
|
|
Title:
|
| | |
risers
|
|
Wording
|
| | |
Risers are required to grade with secured lids over the inlet and outlet of the septic tank. Minimum 24" riser over inlet.
|
|
|
Title:
|
| | |
conventional system monitoring
|
|
Wording
|
| | |
As per Jefferson County Code 8.15 all onsite sewage systems require monitoring. Monitoring shall be provided by an approved entity. THIS SYSTEM IS REQUIRED TO BE INSPECTED EVERY 6 YEARS.
|
|
|
Title:
|
| | |
conventional-asbuilt required
|
|
Wording
|
| | |
An asbuilt drawing and certification of completion by the installer is required prior to final approval.
|
|
|
Title:
|
| | |
surface water setback
|
|
Wording
|
| | |
Setback to any surface waters- 100' required from drainfield and reserve areas. 50' required from tanks.
|
|
|
Title:
|
| | |
protective barriers
|
|
Wording
|
| | |
Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.
|
|
|
Title:
|
| | |
riser on d-box
|
|
Wording
|
| | |
Distribution boxes shall be fitted with a riser to grade, constructed of durable materials and a secured lid, adequately sized to allow visible inspection of the liquid level in the box.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|