Permit Case Summary

Case Number: Search Help

Case Number:SEP2001-00152 Case Status:Finaled Date Received:8/22/2001
Description:per SUB04-34, a BLA, this septic sys serves the main residence under BLD01-480 ADU is filed under SEP00-276. parcel # changed from 027 to 026 Date Issued:9/27/2001
Applicant:HARVEY WINDLE Expiration Date:9/27/2004 12:00:00 AM
Site Address:304 TOTEM RIDGE RD Case Finaled:1/16/2003
Parcel No:901114026 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 1/16/2003
Disposition: DONE
Description: Issue permit (F)
Date Completed: 9/27/2001
Disposition: DONE
Description: Pending letter; add inf (F)
Date Completed: 9/27/2001
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 8/23/2001
Disposition: DONE
Description: Case Entered
Date Completed: 8/23/2001
Disposition:
Description: Stormwater Review-U
Date Completed: 9/27/2001
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 9/27/2001
Disposition: DONE
Description: Initial Site Inspection by HD
Date Completed: 8/28/2001
Disposition: DONE
Description: Print ESA Review Form-F
Date Completed: 8/23/2001
Disposition: DONE
Description: Septic Permit Application (F)
Date Completed: 8/23/2001
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: well setback requirement
Wording Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.

Title: other setbacks req.
Wording Maintain 10' min. setback from water line to any portion of septic system

Title: other setbacks req.
Wording 25 ft. setback from any 100% slope/bank to be maintained with both primary and reserve.

Title: trench depth
Wording MAXIMUM TRENCH DEPTH 30 INCHES

Title: reserve area, alternative
Wording When/if designated reserve area is utilized an alternative system providing an additional level of treatment may be required.

Title: low use water fixures
Wording Low use water fixtures required, 1.6 gal. flush toilets and 2.5 gpm shower heads.

Title: protection from vehicular traffic
Wording All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance.

Title: installed on natural contours
Wording Drainlines are to be installed along the natural contours.

Title: staking of drainfield
Wording Contact designer prior to installation for staking of drainfield area.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from septic tank and drainfield area.

Title: transport line double cased
Wording Any portion of transport line under a driven way is to be double cased or equivalent.

Title: UDC compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.

Title: risers
Wording Risers are required to grade with secured lids over the inlet and outlet of the septic tank. Minimum 24" riser over inlet.

Title: conventional system monitoring
Wording As per Jefferson County Code 8.15 all onsite sewage systems require monitoring. Monitoring shall be provided by an approved entity. THIS SYSTEM IS REQUIRED TO BE INSPECTED EVERY 6 YEARS.

Title: conventional-asbuilt required
Wording An asbuilt drawing and certification of completion by the installer is required prior to final approval.

Title: surface water setback
Wording Setback to any surface waters- 100' required from drainfield and reserve areas. 50' required from tanks.

Title: protective barriers
Wording Permanent barriers are required along/around primary and reserve drainfield areas to protect from parking, driving, and other land disturbing activities prior to final.

Title: riser on d-box
Wording Distribution boxes shall be fitted with a riser to grade, constructed of durable materials and a secured lid, adequately sized to allow visible inspection of the liquid level in the box.

Title: Stormwater BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.