Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
10/9/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
1/26/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pending letter; add inf (F)
|
|
Date Completed:
|
| | |
1/26/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initial Site Inspection
|
|
Date Completed:
|
| | |
1/8/2001
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
12/18/2000
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Review Case
|
|
Date Completed:
|
| | |
1/26/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Critical Area Review
|
|
Date Completed:
|
| | |
1/23/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
12/18/2000
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
12/15/2000
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
asbuilt required
|
|
Wording
|
| | |
An asbuilt drawing and certification of completion by the designer is required prior to final approval.
|
|
|
Title:
|
| | |
well setback requirement
|
|
Wording
|
| | |
Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.
|
|
|
Title:
|
| | |
other setbacks req.
|
|
Wording
|
| | |
100 ft. setback from standing water in the designated wetland area must be maintained.
|
|
|
Title:
|
| | |
dry season installation
|
|
Wording
|
| | |
Dry season installation required.
|
|
|
Title:
|
| | |
trench depth
|
|
Wording
|
| | |
MAXIMUM TRENCH DEPTH 24INCHES
|
|
|
Title:
|
| | |
reserve area, alternative
|
|
Wording
|
| | |
When/if designated reserve area is utilized an alternative system providing an additional level of treatment may be required.
|
|
|
Title:
|
| | |
low use water fixures
|
|
Wording
|
| | |
Low use water fixtures required, 1.6 gal. flush toilets and 2.5 gpm shower heads.
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance. Protective barriers are required around drainfield.
|
|
|
Title:
|
| | |
installed on natural contours
|
|
Wording
|
| | |
Drainlines are to be installed along the natural contours.
|
|
|
Title:
|
| | |
staking of drainfield
|
|
Wording
|
| | |
Contact designer prior to installation for staking of drainfield area. System must be installed in area of soil logs #6 and #9 as shown on site plan and staked in the field by Bernt 1/8/01.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
water tight tank
|
|
Wording
|
| | |
Asphaultic emulsion or equivalent required on septic tank and/or pump chamber.
|
|
|
Title:
|
| | |
final approval
|
|
Wording
|
| | |
Final approval of the sewage disposal permit will be given at the time our office has recieved as-built forms from the designer and inspections from this office have been completed.
|
|
|
Title:
|
| | |
no building permit guarantee
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.
|
|
|
Title:
|
| | |
critical area compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Critical Areas Ordinance for other development on the site.
|
|
|
Title:
|
| | |
critical area waiver cond.
|
|
Wording
|
| | |
Compliance with the conditions of the signed Critical Area Waiver is required.
|
|
|
Title:
|
| | |
risers
|
|
Wording
|
| | |
Risers are required to grade with secured lids over the inlet and outlet of the septic tank. Minimum 24" riser over inlet. Install riser to grade over distibution box.
|
|
|
Title:
|
| | |
MONITORIN-NO HOLD
|
|
Wording
|
| | |
Compliance with monitoring frequency is required in accordance with Table 1 of Jefferson County Ordinance 08-0921-00, On-Site Sewage Code 8.15. This site must be inspected every 6 years or at the time of sale.
|
|