Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
5/7/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
11/29/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pending letter; add inf (F)
|
|
Date Completed:
|
| | |
11/28/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
11/2/2000
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review
|
|
Date Completed:
|
| | |
11/28/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Case
|
|
Date Completed:
|
| | |
11/29/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Critical Area Review
|
|
Date Completed:
|
| | |
11/28/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
11/2/2000
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
well setback requirement
|
|
Wording
|
| | |
Vault setback to all public wells is 100'. 50' required from the river
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage away from the vault area.
|
|
|
Title:
|
| | |
water tight tank
|
|
Wording
|
| | |
Vault to be mono pour and water tight.
|
|
|
Title:
|
| | |
UDC compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Unified Development Code for other/future development on the site.
|
|
|
Title:
|
| | |
holding tank
|
|
Wording
|
| | |
Risers to grade with secured lids shall be located over all compartments. Access ports intended for use as pump-out sites shall be fitted with an impervious pad that slopes towards the access. All pumping and related service must be performed by a Jefferson County licensed septic system pumper. Permit Holder shall maintain and keep operational records which include pumping intervals, sewage volume, disposal site, service and repair records. These records shall be available upon request of the Health officer representative.
|
|
|
Title:
|
| | |
CLOSE PARK PUMP VAULT
|
|
Wording
|
| | |
Per the letter dated 10-31-01 from the State Parks & Recreation Commission the Vault shall be pumped dry prior to November 1st of each year and the east campground closed from November thru March of each year. This is being done as a mittigative factor allowing the Vault toilet to be installed in a flood plain.
|
|
|
Title:
|
| | |
Stormwater BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|