Case Number:SEP1999-00175 Case Status:Finaled Date Received:6/15/1999
Description:SEP94-256 NOW FILED HERE. EES 3/3/09 Date Issued:8/4/1999
Applicant:RONALD HAIRE Expiration Date:8/4/2002 12:00:00 AM
Site Address:103 SYCAMORE ST Case Finaled:1/13/2003
Parcel No:932300022 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: OSS Inspection-6 Months
Date Completed: 7/27/2007
Disposition: DONE
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 1/13/2003
Disposition: DONE
Description: Renew Permit
Date Completed: 7/26/2001
Disposition: DONE
Description: Renew Permit
Date Completed: 7/28/2000
Disposition: DONE
Description: Renewal Notice Printed (F)
Date Completed: 7/26/2000
Disposition: DONE
Description: Issue permit (F)
Date Completed: 8/4/1999
Disposition: ISS
Description: Case Entered
Date Completed: 6/15/1999
Disposition:
Description: Stormwater Review
Date Completed: 6/22/1999
Disposition:
Description: Review Case
Date Completed: 8/4/1999
Disposition: ISS
Description: Critical Area Review
Date Completed: 6/22/1999
Disposition:
Description: Septic Permit Application (F)
Date Completed: 6/16/1999
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: pud monitoring
Wording AS PER WAC 246-272 ALL ALTERNATIVE SYSTEMS REQUIRE MONITORING. THIS MONITORING IS PROVIDED BY AGREEMENT BETWEEN THE JEFFERSON COUNTY ENVIRONMENTAL HEALTH DIVISION AND THE JEFFERSON COUNTY PUBLIC UTILITY DISTRICT #1. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING CONTRACT WITH THE PUD #1 PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM.

Title: pressure test observation
Wording Health Dept. required to observe pressure test, 48 hour notice to be given.

Title: well setback requirement
Wording Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.

Title: trench depth
Wording MAXIMUM TRENCH DEPTH 12 INCHES

Title: protection from vehicular traffic
Wording All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance. Protective barriers are required around drainfield.

Title: dose counter
Wording Dose counters are required in the control panel for all drainfield components.

Title: divert drainage
Wording Divert all sources of drainage, including roof drains away from septic tank and drainfield area.

Title: transport line double cased
Wording Any portion of transport line under a driven way is to be double cased or equivalent.

Title: water tight tank
Wording Asphaultic emulsion or equivalent required on septic tank and/or pump chamber.

Title: no building permit guarantee
Wording Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.

Title: critical area compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Critical Areas Ordinance for other development on the site.

Title: reduced size df
Wording Performance monitoring schedule for treatment systems followed by reduced sized drainfield/infiltrative area shall be :1) Two times per year (once every six months) during the first and second year following installation. 2) One time per year beginning with the third year following installation. 3) In response to complaints or problems. Observation ports to the bottom of the trench are to be installed in at least two places on each drainfield line: One within 10 feet of the beginning of each line and one within 10 feet of the end of each line.

Title: conventional-asbuilt required
Wording An asbuilt drawing and certification of completion by the installer is required prior to final approval.

Title: CUSTOM CONDITION
Wording This system is designed using Best Management Practices for the reduction of nitrogen due to the location of the site in a well head protection area and having excessively well drained soils. BMP's are required per Administrative Rules of the Critical Area Ord. 14-1626-95.