Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
9/13/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Incomplete Installation "I"
|
|
Date Completed:
|
| | |
9/10/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Renewal Notice Printed (F)
|
|
Date Completed:
|
| | |
9/10/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Renewal Notice Printed (F)
|
|
Date Completed:
|
| | |
8/24/2000
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Renew Permit
|
|
Date Completed:
|
| | |
9/3/1999
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Renewal Notice Printed (F)
|
|
Date Completed:
|
| | |
8/31/1999
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue permit (F)
|
|
Date Completed:
|
| | |
9/3/1998
|
|
Disposition:
|
| | |
ISS
|
|
|
Description:
|
| | |
Pending letter; add inf (F)
|
|
Date Completed:
|
| | |
9/3/1998
|
|
Disposition:
|
| | |
P
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
7/9/1998
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review
|
|
Date Completed:
|
| | |
7/15/1998
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Review Case
|
|
Date Completed:
|
| | |
9/3/1998
|
|
Disposition:
|
| | |
ISS
|
|
|
Description:
|
| | |
Critical Area Review
|
|
Date Completed:
|
| | |
8/6/1998
|
|
Disposition:
|
| | |
OKAY
|
|
|
Description:
|
| | |
PUD contract required
|
|
Date Completed:
|
| | |
10/9/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
AsBuilt from engineer req
|
|
Date Completed:
|
| | |
9/13/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Pressure test required
|
|
Date Completed:
|
| | |
10/20/1999
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Easement required
|
|
Date Completed:
|
| | |
9/17/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
7/10/1998
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
pud monitoring
|
|
Wording
|
| | |
AS PER WAC 246-272 ALL ALTERNATIVE SYSTEMS REQUIRE MONITORING. THIS MONITORING IS PROVIDED BY AGREEMENT BETWEEN THE JEFFERSON COUNTY ENVIRONMENTAL HEALTH DIVISION AND THE JEFFERSON COUNTY PUBLIC UTILITY DISTRICT #1. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING CONTRACT WITH THE PUD #1 PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM.
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test, 48 hour notice to be given.
|
|
|
Title:
|
| | |
well setback requirement
|
|
Wording
|
| | |
Setbacks to all wells- 100' required from drainfield and reserve areas. 50' required from tanks and effluent transport lines.
|
|
|
Title:
|
| | |
other setbacks req.
|
|
Wording
|
| | |
50 ft. setback from surface water to tanks to be maintained.
|
|
|
Title:
|
| | |
dry season installation
|
|
Wording
|
| | |
Dry season installation required.
|
|
|
Title:
|
| | |
easement
|
|
Wording
|
| | |
Recorded easement required for primary and/or reserve drainfields. Easement recorded 7/98 with the Jefferson County Auditors office.
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance. Protective barriers are required around drainfield.
|
|
|
Title:
|
| | |
installed on natural contours
|
|
Wording
|
| | |
Drainlines are to be installed along the natural contours.
|
|
|
Title:
|
| | |
staking of drainfield
|
|
Wording
|
| | |
Contact designer prior to installation for staking of drainfield area.
|
|
|
Title:
|
| | |
dose counter
|
|
Wording
|
| | |
Dose counters are required in the control panel for all drainfield components.
|
|
|
Title:
|
| | |
divert drainage
|
|
Wording
|
| | |
Divert all sources of drainage, including roof drains away from septic tank and drainfield area.
|
|
|
Title:
|
| | |
transport line double cased
|
|
Wording
|
| | |
Any portion of transport line under a driven way is to be double cased or equivalent.
|
|
|
Title:
|
| | |
water tight tank
|
|
Wording
|
| | |
Asphaultic emulsion or equivalent required on septic tank and/or pump chamber.
|
|
|
Title:
|
| | |
no building permit guarantee
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.
|
|
|
Title:
|
| | |
critical area compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Critical Areas Ordinance for other development on the site.
|
|
|
Title:
|
| | |
minimum land NOTICE TO TITLE
|
|
Wording
|
| | |
This permit is granted based on the approved waiver from the state requirements of 1 acre of minimum land area where an individual well is used. The waiver was approved based on land area averaging where the drainfield is on a separate parcel and when averaged with the residence the land area is greater than 1 acre.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
Compliance with conditions of approved Road Crossing permit required.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
Existing septic tank must be tested to be water tight by the designer, of 1000 gallon capacity and two compartments to be used.
|
|
|
Title:
|
| | |
WELL ABANDONMENT
|
|
Wording
|
| | |
Verification of proper abandonment of the well to be provided to this office prior to final approval of the permit.
|
|