Permit Case Summary

Case Number: Search Help

Case Number:SEP1995-00328 Case Status:Finaled Date Received:7/22/1996
Description:serves mobile home to south of parcel. see also SOM2021-01019 pump report only for 'cabin' Date Issued:8/8/1996
Applicant:ROSWELL DUPPENTHALER TRUSTEE Expiration Date:8/8/1997 12:00:00 AM
Site Address:65 SPOTTED OWL LN Case Finaled:1/6/1997
Parcel No:502151034 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Sanit.Survey Attempted by JCPH
Date Completed: 6/18/2009
Disposition: DONE
Description: OSS Inspection-2 Year
Date Completed: 5/30/2003
Disposition: DONE
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 1/6/1997
Disposition:
Description: PUD Monitoring Contract ltr"L"
Date Completed: 10/17/1996
Disposition:
Description: Partial Final/cont Renewal "T"
Date Completed: 9/3/1996
Disposition:
Description: Issue permit (F)
Date Completed: 8/8/1996
Disposition: ISSU
Description: REDESIGN SUBMITTED (F)
Date Completed: 7/22/1996
Disposition:
Description: Case Entered
Date Completed: 10/23/1995
Disposition:
Description: Review Case
Date Completed: 8/8/1996
Disposition: ISSU
Description: Critical Area Review Complete
Date Completed: 11/8/1995
Disposition:
Description: Septic Permit Application (F)
Date Completed: 10/23/1995
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: pud monitoring
Wording AS PER WAC 246-272 ALL ALTERNATIVE SYSTEMS REQUIRE MONITORING. THIS MONITORING IS PROVIDED BY AGREEMENT BETWEEN THE JEFFERSON COUNTY ENVIRONMENTAL HEALTH DIVISION AND THE JEFFERSON COUNTY PUBLIC UTILITY DISTRICT #1. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING CONTRACT WITH THE PUD #1 PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM.

Title: pressure test observation
Wording Health Dept. required to observe pressure test, 48 hour notice to be given.

Title: well setback requirement
Wording 100 ft. setback to all wells to be maintained

Title: other setbacks req.
Wording 25 ft. setback from bank to be maintained.

Title: trench depth
Wording MAXIMUM TRENCH DEPTH 18 INCHES

Title: reserve area, alternative
Wording When/if designated reserve area is utilized an enhanced treatment system may be required.

Title: low use water fixures
Wording Low use water fixtures recommended, 1.6 gal. flush toilets and 2.5 gpm shower heads.

Title: protection from vehicular traffic
Wording All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance. Protective barriers are required around drainfield.

Title: installed on natural contours
Wording Drainlines are to be installed along the natural contours.

Title: staking of drainfield
Wording Contact designer prior to installation for staking of drainfield area.

Title: dose counter
Wording Dose counters are required in the control panel for all drainfield components.

Title: divert drainage
Wording Divert all sources of drainage away from septic tank and drainfield area.

Title: transport line double cased
Wording Any portion of transport line under a driven way is to be double cased or equivalent.

Title: no building permit guarantee
Wording Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.

Title: critical area compliance
Wording Approval of this sewage disposal permit does not preclude the permit holder from complying with the Critical Areas Ordinance for other development on the site.