Description:
|
| | |
OSS Inspection-2 Year
|
|
Date Completed:
|
| | |
6/25/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
SEPTIC PERMIT FINALED "F"
|
|
Date Completed:
|
| | |
2/5/1999
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Renewal Notice Printed (F)
|
|
Date Completed:
|
| | |
2/1/1999
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
PUD contract required
|
|
Date Completed:
|
| | |
2/19/1998
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
AsBuilt from engineer req
|
|
Date Completed:
|
| | |
2/19/1998
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Pressure test required
|
|
Date Completed:
|
| | |
1/2/1998
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
PUD Monitoring Contract ltr"L"
|
|
Date Completed:
|
| | |
2/2/1998
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Renewal Notice Printed (F)
|
|
Date Completed:
|
| | |
2/2/1998
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Partial Final/cont Renewal "T"
|
|
Date Completed:
|
| | |
1/5/1998
|
|
Disposition:
|
| | |
T
|
|
|
Description:
|
| | |
Redesign APPR & ISSUED-newdate
|
|
Date Completed:
|
| | |
2/21/1997
|
|
Disposition:
|
| | |
ISS
|
|
|
Description:
|
| | |
Review Case
|
|
Date Completed:
|
| | |
2/21/1997
|
|
Disposition:
|
| | |
PD
|
|
|
Description:
|
| | |
REDESIGN SUBMITTED (F)
|
|
Date Completed:
|
| | |
6/11/1996
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Review Case
|
|
Date Completed:
|
| | |
2/21/1996
|
|
Disposition:
|
| | |
PD
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/18/1995
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Review Case
|
|
Date Completed:
|
| | |
10/5/1995
|
|
Disposition:
|
| | |
PD
|
|
|
Description:
|
| | |
Critical Area Review Complete
|
|
Date Completed:
|
| | |
9/26/1995
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Inspection
|
|
Date Completed:
|
| | |
6/4/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Permit Application (F)
|
|
Date Completed:
|
| | |
8/22/1995
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
pud monitoring
|
|
Wording
|
| | |
AS PER WAC 246-272 ALL ALTERNATIVE SYSTEMS REQUIRE MONITORING. THIS MONITORING IS PROVIDED BY AGREEMENT BETWEEN THE JEFFERSON COUNTY ENVIRONMENTAL HEALTH DIVISION AND THE JEFFERSON COUNTY PUBLIC UTILITY DISTRICT #1. THIS SEWAGE DISPOSAL SYSTEM WILL REQUIRE AN ACTIVE MONITORING CONTRACT WITH THE PUD #1 PRIOR TO FINAL APPROVAL OF THE SEWAGE DISPOSAL SYSTEM.
|
|
|
Title:
|
| | |
pressure test observation
|
|
Wording
|
| | |
Health Dept. required to observe pressure test, 48 hour notice to be given.
|
|
|
Title:
|
| | |
well setback requirement
|
|
Wording
|
| | |
100 ft. setback to all wells to be maintained
|
|
|
Title:
|
| | |
other setbacks req.
|
|
Wording
|
| | |
50 ft. setback from wells to effluent transport line to be maintained. 10' setback to water lines from any portion of onsite sewage system.
|
|
|
Title:
|
| | |
dry season installation
|
|
Wording
|
| | |
Dry season installation required.
|
|
|
Title:
|
| | |
low use water fixures
|
|
Wording
|
| | |
Low use water fixtures required, 1.6 gal. flush toilets and 2.5 gpm shower heads.
|
|
|
Title:
|
| | |
protection from vehicular traffic
|
|
Wording
|
| | |
All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance. Protective barriers are required around drainfield.
|
|
|
Title:
|
| | |
dose counter
|
|
Wording
|
| | |
Dose counters are required in the control panel for all drainfield components.
|
|
|
Title:
|
| | |
transport line double cased
|
|
Wording
|
| | |
Any portion of transport line under a driven way is to be double cased or equivalent.
|
|
|
Title:
|
| | |
water tight tank
|
|
Wording
|
| | |
Asphaultic emulsion or equivalent required on septic tank and/or pump chamber.
|
|
|
Title:
|
| | |
no building permit guarantee
|
|
Wording
|
| | |
Approval/issuance of a sewage disposal permit does not guarantee the approval of other development or a building permit on this site. Compliance with other Jefferson County and Washington State Codes is required.
|
|
|
Title:
|
| | |
critical area compliance
|
|
Wording
|
| | |
Approval of this sewage disposal permit does not preclude the permit holder from complying with the Critical Areas Ordinance for other development on the site.
|
|
|
Title:
|
| | |
risers
|
|
Wording
|
| | |
Risers are required to grade with secured lids over the inlet and outlet of the septic tank. Minimum 24" riser over inlet.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
Road crossing permit required from State Dept. of Transportation for crossing State Route 116 with effluent transport line. Permit issued 2-3-97. Compliance with conditions of permit required.
|
|