Permit Case Summary

Case Number: Search Help

Case Number:SEP1994-00060 Case Status:Finaled Date Received:2/22/1994
Description: Date Issued:3/1/2002
Applicant:DON WILLIAMS Expiration Date:10/10/2001 12:00:00 AM
Site Address:214 N BEACH DR Case Finaled:9/28/2004
Parcel No:935700009 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: OSS Inspection-6 Months
Date Completed: 5/4/2005
Disposition: DONE
Description: SEPTIC PERMIT FINALED "F"
Date Completed: 9/28/2004
Disposition: DONE
Description: Incomplete Installation "I"
Date Completed: 3/1/2002
Disposition: DONE
Description: Renew Permit
Date Completed: 10/10/2000
Disposition: DONE
Description: Renew Permit
Date Completed: 3/11/1999
Disposition:
Description: Renewal Notice Printed (F)
Date Completed: 2/26/1999
Disposition:
Description: Renew Permit
Date Completed: 2/26/1998
Disposition:
Description: PUD contract required
Date Completed: 1/31/2001
Disposition: DONE
Description: AsBuilt from engineer req
Date Completed: 9/27/2004
Disposition: DONE
Description: Pressure test required
Date Completed: 12/12/2000
Disposition: DONE
Description: Renewal Notice Printed (F)
Date Completed: 2/2/1998
Disposition:
Description: Renew Permit
Date Completed: 3/14/1997
Disposition:
Description: Renewal Notice Printed (F)
Date Completed: 2/24/1997
Disposition:
Description: Renew Permit
Date Completed: 3/7/1996
Disposition:
Description: Renewal Notice Printed (F)
Date Completed: 2/27/1996
Disposition:
Description: Renew Permit
Date Completed: 4/18/1995
Disposition:
Description: Renewal Notice Printed (F)
Date Completed: 2/28/1995
Disposition:
Description: Case Entered
Date Completed: 2/22/1994
Disposition:
Description: Review Case
Date Completed: 3/9/1994
Disposition: PP
Description: Septic Permit Application (F)
Date Completed: 2/24/1994
Disposition:
Description: Issue permit (F)
Date Completed: 3/14/1994
Disposition: ISS

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: pud monitoring
Wording PUD monitoring contract is required

Title: pressure test observation
Wording Health Dept. required to observe pressure test, 48 hour notice to be given.

Title: setback requirement
Wording 100 ft. setback to surface water to be maintained

Title: low use water fixures
Wording Low use water fixtures required, 1.6 gal. flush toilets and 2.5 gpm shower heads.

Title: protection from vehicular traffic
Wording All components of the septic system are to be completely protected from vehicular traffic or mechanical disturbance. Protective barriers are required around drainfield.

Title: dose counter
Wording Dose counters are required in the control panel for all drainfield components.

Title: transport line double cased
Wording Any portion of transport line under a driven way is to be double cased or equivalent.

Title: water tight tank
Wording Asphaultic emulsion or equivalent required on septic tank and/or pump chamber.