Permit Case Summary

Case Number: Search Help

Case Number:SDP2018-00020 Case Status: Date Received:10/4/2018
Description:Shoreline Exemption for Maintenance to an Existing Parking Area including removal of a 3500 sq ft. concrete slap, regrading and replacement of Interpretive board for an existing recreational facility. Date Issued:11/6/2018
Applicant: WA DEPT OF FISH AND WILDLIFE Expiration Date:11/6/2023 12:00:00 AM
Site Address:POINT WHITNEY RD Case Finaled:
Parcel No:601071002 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 11/7/2019
Disposition:
Description: Approve Exemption-UF
Date Completed: 11/6/2018
Disposition: DONE
Description: A Clock Interrupt
Date Completed: 11/6/2018
Disposition: DONE
Description: Additional Info Request-DRD
Date Completed: 11/6/2018
Disposition: DONE
Description: Consistency Review-U
Date Completed: 11/6/2018
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 11/6/2018
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 11/6/2018
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 11/6/2018
Disposition: DONE
Description: Case Entered
Date Completed: 10/4/2018
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described in the JARPA dated October 3, 2018 and submitted with the Shoreline Exemption application above shall receive separate review from this Department.

Title: Progress towards completion
Wording Substantial progress towards completion of the project shall be performed within five years of the issuance of the permit.

Title: Exempt Maintenance Condition
Wording The development shall be essentially the same as the original in location, size, configuration, and external appearance.

Title: JARPA AND SWPPP
Wording The Applicant shall comply with the JARPA and Stormwater Pollution Prevention Plan as submitted by the applicant on October 3, and October 31, 2018 respectively.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: Hydraulic Code/HPA Check
Wording Prior to commencing development activity, proponent is responsible for informing the Washington Department of Fish and Wildlife (WDFW) in order for WDFW to determine whether this action is subject to the Washington State Hydraulic Code (Chapter 220-10 WAC). Hydraulic Project Approval (HPA) is required for all hydraulic projects, which are defined as construction or performance of other work that will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state.

Title: Comply with HPA
Wording In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-FEMA
Wording The project is exempt under section 7.1 E of the Model Washington NFIP-ESA Ordinance from the requirements of a Flood Development Permit JCC 15.

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on (date) for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review, the following ESAs were confirmed to be present on the subject property: Conservancy Shoreline Designation; FEMA Flood Zone A.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(3).

Title: F-Site Plan Changes
Wording The site plan as submitted with the Shoreline Exemption application on October 3, 2018 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated November 6, 2018 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for a Shoreline Exemption for Repair and Maintenance to an Existing Recreational Facility only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: ZONING
Wording The parcel has been designated as Parks and Recreation under the Jefferson County Comprehensive Land Use Map effective August 28, 1998.

Title: F-SDP Exemption Section
Wording The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section JCC 18.25.560(2) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.