Description:
|
| | |
Status updtd - Energov Convrsn
|
|
Date Completed:
|
| | |
10/4/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
11/6/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Exemption-UF
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Approve Exemption-UF
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
9/6/2016
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
DRD Reviewer Letter (F)
|
|
Date Completed:
|
| | |
8/22/2016
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
9/13/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/13/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/13/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
9/6/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
9/12/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/3/2016
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
VEGETATION REMOVAL
|
|
Wording
|
| | |
All trees and understory lying outside of the defined tree removal areas on the site plan shall be retained during clearing for utilities.
|
|
|
Title:
|
| | |
DIRECTIONAL FELLING
|
|
Wording
|
| | |
Damage to vegetation retained during initial clearing activities shall be minimized by directional felling of trees to avoid critical areas and vegetation to be retained.
|
|
|
Title:
|
| | |
STUMP CLEARING
|
|
Wording
|
| | |
Retained trees, understory and stumps may subsequently be cleared only if such clearing is necessary to complete the proposal involved in the project application.
|
|
|
Title:
|
| | |
VEGETATIVE DEBRIS
|
|
Wording
|
| | |
Vegetative debris shall be properly managed by mulching/leaving in place as habitat and soil amendment, composting on-site, or removing and disposing of off-site. The dumping of vegetative debris, including grass clippings and yard waste, in shoreline areas is strongly discouraged, especially when slope stability and water quality would be threatened.
|
|
|
Title:
|
| | |
COMPLY WITH TREE REMOVAL NOTES
|
|
Wording
|
| | |
Any vegetation removal associated with the project shall comply with the Tree Removal Notes on the approved plans.
|
|
|
Title:
|
| | |
UTILITIES FLOOD
|
|
Wording
|
| | |
All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of flood waters into the systems.
|
|
|
Title:
|
| | |
CONSTRUCTION MATERIALS
|
|
Wording
|
| | |
Construction Materials and Methods: (1) All new construction and substantial improvements shall be constructed with materials and utility equipment resistant to flood damage; and (2) All new construction and substantial improvements shall be constructed using methods and practices that minimize flood damage.
|
|
|
Title:
|
| | |
SANITARY SEWAGE SYSTEMS-FLOOD
|
|
Wording
|
| | |
New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of flood waters into the systems and discharges from the systems into flood waters;
|
|
|
Title:
|
| | |
SUBSTANTIAL COMPLETION
|
|
Wording
|
| | |
Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.
|
|
|
Title:
|
| | |
RESTORATION BMPS
|
|
Wording
|
| | |
The applicant shall immediately restore the installation sites to their pre-project condition to the maximum extent possible.
|
|
|
Title:
|
| | |
EROSION CONTROL MEASURES
|
|
Wording
|
| | |
Erosion control measures must be in place prior to any clearing, grading, or construction. These control measures must be effective to prevent stormwater runoff from carrying soil and other pollutants into surface water or storm drains that lead to waters of the state. Sand, silt, clay particles, and soil will damage aquatic habitat and are considered to be pollutants.
|
|
|
Title:
|
| | |
SOIL STOCKPILES
|
|
Wording
|
| | |
Soil in stockpiles should be stabilized or protected with sediment-trapping measures to prevent soil loss. All exposed areas of final grade or areas that are not scheduled for work, whether at final grade or otherwise, shall not remain exposed and un-worked for more than two days, between October 1 and April 30. Between May 1 and September 30, no soils shall remain exposed and un-worked for more than 7 days.
|
|
|
Title:
|
| | |
SWPPP PUBLIC WORKS COMMENT
|
|
Wording
|
| | |
Proponents are required to consider the Construction Stormwater Pollution Prevention Plan elements and develop controls for the elements that pertain to the project. The applicant has prepared a TESC/Staging Plan for the project. The proponent shall comply with the submitted TESC Plan in order to meet Minimum Requirement #2 of the 2014 Department of Ecology Stormwater Management Manual.
|
|
|
Title:
|
| | |
MARK CLEARING LIMITS
|
|
Wording
|
| | |
THE LIMITS OF CLEARING SHALL BE CLEARLY MARKED ON THE PROPERTY. PLASTIC, METAL, OR STAKE WIRE FENCING SHALL BE INSTALLED AS SHOWN ON THE APPROVED SITE PLAN PRIOR TO BEGINNING ANY GROUND-DISTURBING ACTIVITIES, AND SHALL BE INSTALLED TO COMPLY WITH SPECIFICATIONS IN THE 2012 STORMWATER MANAGEMENT MANUAL FOR WESTERN WASHINGTON (BMP C103). HEAVY EQUIPMENT SHALL NOT DISTURB TOP SOIL OR VEGETATION BEYOND THE CLEARING LIMITS.
|
|
|
Title:
|
| | |
UTILITIES NNL - JCC 18.25.560(6)
|
|
Wording
|
| | |
Outfall pipelines and diffusers are water-dependent but shall be located to minimize adverse effects on shoreline ecological functions and processes or adverse impacts upon shoreline resources and values.
|
|
|
Title:
|
| | |
Follow Flood Ordinance
|
|
Wording
|
| | |
Flood hazard reduction measures are to be used as required by the Jefferson County Flood Damage Prevention Ordinance 07-0515-06 (Jefferson County Code Chapter 15.15).
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
F-SHORELINE EXEMPTION
|
|
Wording
|
| | |
The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section 18.25.560(2) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.
|
|
|
Title:
|
| | |
F-CRITICAL AREAS EXEMPT
|
|
Wording
|
| | |
The proposal is exempt from critical areas per JCC 18.22.070 (5).
|
|
|
Title:
|
| | |
F-FLOOD
|
|
Wording
|
| | |
The proposal will be located in Dosewallips River, in an area that is mapped on the Federal Emergency Management Agency Flood Insurance Rate Map (panel 530069 1235B) as Zone A. The proposed project is subject to the requirement for a flood development permit, which is incorporated into this decision. The proposal meets the definition of development but not structure in the flood damage prevention ordinance, as codified in JCC 15.15.050.
|
|
|
Title:
|
| | |
F-FLOOD LEVELS
|
|
Wording
|
| | |
The proposed project will not result in any increase in flood levels during the occurrence of base flood discharges.
|
|
|
Title:
|
| | |
F-FEMA BI-OP EXEMPT
|
|
Wording
|
| | |
In accordance with the flood model ordinance Section 7.2, (A): repairs or remodeling of an existing structure that are not a substantial improvement or a repair of substantial damage is allowed without a FEMA biological assessment.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on 8/22/2016for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: FEMA Special Flood Hazard Area: Zone A, stable shoreline slope stability, Type Fish and Non-Fish Bearing Stream AND Shoreline Fish and Wildlife Habitat Conservation Area, bald eagle nest, great blue heron colony heritage point, harlequin duck and elk breeding area priority habitat, wetlands, seismic hazard, slight landslide hazard, susceptible aquifer recharge area, coastal seawater intrusion protection zone, disconnected channel migration zone.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Geohazard Area
|
|
Wording
|
| | |
Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.
|
|
|
Title:
|
| | |
F-Coastal SIPZ
|
|
Wording
|
| | |
The parcel is located within a coastal SIPZ (seawater intrusion protection zone) according to the County GIS map. There are voluntary and mandatory measures identified in the Jefferson County Seawater Intrusion Policy (Resolution 61-02, effective September 23, 2002) that apply to well drilling proposals and building permit applications on existing lots of record.
A Coastal SIPZ is defined as: all islands and area within one-quarter mile of marine shoreline, but no history of chloride concentration above 100 mg/L in groundwater sources within 1000 feet.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Washington Department of Parks and Recreation determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1(b)(iv); WAC 197-11-800(23)(g).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the utility repair and replacement application on August 3, 2016 and revised Sheet 4 submitted September 30, 2016 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated September 13, 2016 and Sheet 4 dated October 6, 2016 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a repair and replacement of failing campground utilities only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|