Permit Case Summary

Case Number: Search Help

Case Number:SDP2013-00033 Case Status: Date Received:7/1/2013
Description:PERMIT RE-ISSUED WITH A FIVE-YEAR EXPIRATION DATE, AS ALLOWED UNDER JCC 18.25.550. SUBSTANTIAL PROGRESS WAS MADE TOWARDS CONSTRUCTION BY NOSC WITHIN DISCOVERY BAY, AND CONSTRUCTION OF THE TRAIL SEGMENT MUST BE COMPLETED WITHIN FIVE YEARS OF THE ORIGINAL ISSUE DATE (WHICH WAS MARCH 18, 2014). Shoreline substantial development and flood development permits for Discovery Bay and Snow Creek restoration projects, waterline replacement project, and Olympic Discovery Trail project. Proposal is located at the south end of Discovery Bay and is subject to review under SEPA. The applicant has submitted a geotechnical report, wetland delineation report, habitat management plan, and Section 7 consultation reports. Date Issued:8/15/2016
Applicant: STATE OF WASHINGTON -FISH/WDLF Expiration Date:8/15/2018 12:00:00 AM
Site Address:282023 HWY 101 Case Finaled:
Parcel No:902242005 Other Cases Parcel Data Map It Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: Approve SDP Permit-UF
Date Completed: 8/15/2016
Disposition: DONE
Description: DCD Review Time
Date Completed: 3/31/2014
Disposition: PEND
Description: DCD Review Time
Date Completed: 3/31/2014
Disposition: PEND
Description: Approve SDP Permit-UF
Date Completed: 3/18/2014
Disposition: DONE
Description: Hearing Date
Date Completed: 3/18/2014
Disposition: DONE
Description: DCD Review Time
Date Completed: 2/28/2014
Disposition: PEND
Description: DCD Review Time
Date Completed: 2/28/2014
Disposition: PEND
Description: DCD Review Time
Date Completed: 2/28/2014
Disposition: PEND
Description: DCD Review Time
Date Completed: 2/28/2014
Disposition: PEND
Description: Hearing Exam PH Notice-APO-UF
Date Completed: 2/7/2014
Disposition: DONE
Description: Hearing Exam PH Notice-Pub-UF
Date Completed: 2/7/2014
Disposition: DONE
Description: DCD Review Time
Date Completed: 1/31/2014
Disposition: PEND
Description: DCD Review Time
Date Completed: 1/27/2014
Disposition: PEND
Description: DCD Review Time
Date Completed: 1/27/2014
Disposition: PEND
Description: DCD Review Time
Date Completed: 12/30/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 12/23/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 12/17/2013
Disposition: PEND
Description: Det. of Completeness-UF
Date Completed: 12/16/2013
Disposition: DONE
Description: A Clock Interrupt
Date Completed: 3/18/2014
Disposition: DONE
Description: Additional Info Request-DRD
Date Completed: 3/18/2014
Disposition: DONE
Description: DCD Review Time
Date Completed: 12/13/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 12/12/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 12/11/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 12/11/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 10/31/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 10/23/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 10/22/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 10/22/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 10/22/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 10/22/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 10/22/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 10/22/2013
Disposition: PEND
Description: DCD Review Time
Date Completed: 10/18/2013
Disposition: PEND
Description: Ntc of App +30-Publish-UF
Date Completed: 10/18/2013
Disposition: DONE
Description: Ntc of App +30-APO-UF
Date Completed: 10/18/2013
Disposition: DONE
Description: Ntc of App +30-Publish-UF
Date Completed: 10/18/2013
Disposition: DONE
Description: Ntc of App +30-APO-UF
Date Completed: 10/18/2013
Disposition: DONE
Description: DRD Reviewer Letter (F)
Date Completed: 10/18/2013
Disposition: DONE
Description: A Clock Interrupt
Date Completed: 9/4/2013
Disposition:
Description: Additional Info Request-DRD
Date Completed: 9/4/2013
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 8/28/2013
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 3/18/2014
Disposition: DONE
Description: Consistency Review-U
Date Completed: 3/18/2014
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 3/18/2014
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 3/18/2014
Disposition: DONE
Description: Septic Review Complete-U
Date Completed: 3/18/2014
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 8/28/2013
Disposition: DONE
Description: Case Entered
Date Completed: 7/1/2013
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: HE CONDITIONS
Wording The applicant shall comply with the following conditions: 1. Prior to constructing the trail, the applicant shall obtain a building permit from Jefferson County Department of Community Development. Stamped, engineered drawings shall be included in the building application submittal. 2. Prior to removing the railroad trestle, a demolition permit is needed (with ORCAA approval). 3. Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit. 4. The applicant shall adhere to all Hydraulic Project Approval requirements. 5. Prior to issuance of a building permit for the proposal, the applicant shall contact Dan DaFoe with Washington Department of Fish and Wildlife at (360) 457-2516 to ensure compliance with Hydraulic Project Approval requirements. 6. The applicant shall obtain a permit from the U.S. Army Corps of Engineers prior to beginning any work on this project. 7. Any damage to proposed structures shall be repaired or removed as soon as practicable. At the end of the useful life of any structures, they will be removed as soon as practicable. 8. The applicant shall adhere to all design recommendations in the geotechnical report prepared by Landau Associates. 9. The applicant shall adhere to all restoration and waterline installation plan sheets submitted to DCD for this project. 10. The applicant shall implement the Site Preparation and TESC Plan prepared for this project and shall ensure all applicable BMPs are in place to protect water quality. 11. The applicant shall comply with any applicable requirements in the U.S. Coast Guard Private Aids to Navigation. 12. Waterlines shall be located a minimum of 10 feet from all septic components. 13. Prior to completion and final signoff of this project, the waterline replacement approval by Washington Department of Health (WDOH) under ODW Project #13-0702 shall be signed off as complete by WDOH. Confirmation from WDOH is required. 14. Sewage effluent transport lines shall be protected from vehicular traffic and disturbance. 15. Any soils moved offsite shall be disposed of at an approved permitted location. 16. For the Snow Creek Estuary portion of the project, no land disturbing activities that result in the presence of surface water within 100 feet of the existing drainfield easement serving the motel owned by Walter Moa shall take place for a minimum of one (1) year after the onsite sewage system stops receiving effluent or testing shows less than 30cfu/100ml enteric bacteria per the 2012 EPA guidelines for recreational waters. 17. For the Maynard Shoreline portion of the project, soils to be excavated shall be screened for contamination prior to being placed either onsite or offsite. The number of samples needed will be dependent upon the volume removed. See the chart in Exhibit 50 and https://fortress.wa.gov/ecy/publications/publications/1009057.pdf. 18. This project is to relocate an existing waterline for the Moa-Tel Water System #07816 and does not include review or approval of additional water connections. The water system is currently at capacity and has no available additional water connections. Any future water connections, beyond what has previously been approved by Washington State Department of Health, requires a separate application that shows compliance with WDOH requirements for the water system and Washington State Department of Ecology requirements for water rights. 19. Jefferson County Public Works will coordinate with Mr. Jafay regarding the timing and type of traffic control utilized on U.S. 101 during the trail construction portion of the project, if required. The applicant shall work to provide a seamless and immediate disconnect from the old waterline and reconnection to the new waterline. The applicant will also coordinate with Mr. Jafay regarding the timing and type of traffic control utilized on U.S. 101 during the waterline relocation and other aspects of the project that require such control and are not within the jurisdiction of Jefferson County Public Works. 20. The applicant will work with Kurt Jafay to provide low growth plantings along the shoreline in front of his parcels such that the current views of Discovery Bay are maintained.