Permit Case Summary

Case Number: Search Help

Case Number:SDP2009-00057 Case Status: Date Received:7/29/2009
Description:SHORELINE EXEMPTION - dock repair and maintenance Date Issued:10/8/2009
Applicant: PORT TOWNSEND PAPER CORP Expiration Date:10/8/2010 12:00:00 AM
Site Address:100 PAPER MILL HILL RD Case Finaled:
Parcel No:001152006 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 4/6/2018
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 10/8/2009
Disposition: DONE
Description: Review Complete-U
Date Completed: 10/8/2009
Disposition: DONE
Description: Case Entered
Date Completed: 7/29/2009
Disposition:
Description: App Substantially Complete-U
Date Completed: 10/8/2009
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 10/8/2009
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 10/8/2009
Disposition: DONE
Description: Consistency Review-U
Date Completed: 10/8/2009
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.

Title: Min Use of Hazardous Materials
Wording The design, location, and construction of docks, piers, and floats, as well as their subsequent use, shall avoid adverse effects on fish, shellfish, wildlife, marine vegetation, water quality, and geohydraulic processes. Construction methods shall minimize the use of materials hazardous to the environment.

Title: Treated Materials Must be Cured
Wording All lumber and other materials treated with preservative shall be sufficiently cured to minimize leaching into the water or shore bed, in accordance with the Best Management Practices approved by the Washington Department of Fish and Wildlife.

Title: Minimize Hazards to Users
Wording Docks, piers, floats and boat houses shall be designed and constructed to minimize hazards to users and to be capable of withstanding the historic extremes of wind, wave, and tides at their location.

Title: Progress towards completion
Wording Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.

Title: Exempt Maintenance Condition
Wording The development shall be essentially the same as the original in location, size, configuration, and external appearance.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: Comply with HPA
Wording In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.

Title: Army Corps Check
Wording Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-HPA & ARMY CORPS
Wording Issues related to over-water develoment activities (including materials, methods, timing, etc.) will be addressed by the Washington Department of Fish and Wildlife HPA and/or U.S. Army Corps of Engineers Section 404 permit.

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on August 27, 2007 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review, the following ESAs were confirmed to be present on the subject property: urban shoreline designation, modified shoreline slope stability, seismic hazards, fish and wildlife conservation areas, susceptible aquifer recharge area, and flood hazard.

Title: F-Aquifer Recharge Area
Wording Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.

Title: F-Susc. Aquifer Recharge Area
Wording Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.

Title: F-Geohazard Area
Wording Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.

Title: F-HPA Issued
Wording The Washington Department of Fish and Wildlife issued Hydraulic Project Approval (HPA) for this activity on April 1, 2009 under Control Number 116668-1. The HPA expires on February , 14, 2014.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(3) & (6).

Title: F-Site Plan Changes
Wording The site plan as submitted with the Shoreline Exemption application on July 29, 2009 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated October 8, 2009 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for a Shoreline Exemption for Dock Repair & Maintenance only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: F-SDP Exemption Section
Wording The Development Review Division finds that this proposal is consistent with Shoreline Master Program JCC Chapter 18.25 and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.