Permit Case Summary

Case Number: Search Help

Case Number:SDP2008-00010 Case Status: Date Received:3/5/2008
Description:As part of the Governor's effort to protect and restore Puget Sound, Fort Flagler State Park proposes to update their existing on-site sewer systems into one consolidated system utilizing a MBR (membrane bio-reactor) wastewater treatment plant. The proposal also involves the addition of electrical and water hook-ups to the existing campground RV sites, but will not increase the number of sites. This project requires a Shoreline Substantial Development permit for a Conditional Use permit and a Zoning Conditional Discretionary Use permit for a Minor Utility and will be processed under the Optional Consolidated Permit Processing JCC 18.40.030(2). Public notice and a public hearing are required. Washington State Parks has assumed environmental review Lead Agency status and issued a Determination of Non-significance for this proposal on March 5, 2008. Date Issued:7/1/2008
Applicant: STATE OF WASHINGTON PARKS Expiration Date:7/1/2010 12:00:00 AM
Site Address:10541 FLAGLER RD Case Finaled:
Parcel No:021180000 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Status updtd - Energov Convrsn
Date Completed: 10/4/2022
Disposition: DONE
Description: File Archived
Date Completed: 4/4/2018
Disposition: DONE
Description: Issue SDP Permit
Date Completed: 7/1/2008
Disposition: DONE
Description: Ntc of Dec Apprvl/Appl Inst-UF
Date Completed: 7/1/2008
Disposition: DONE
Description: Hearing Exam PH Notice-Pub-UF
Date Completed: 5/20/2008
Disposition: DONE
Description: Hearing Exam PH Notice-APO-UF
Date Completed: 5/20/2008
Disposition: DONE
Description: Ntc of App +30-Publish-UF
Date Completed: 4/7/2008
Disposition: DONE
Description: Ntc of App +30-APO-UF
Date Completed: 4/7/2008
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 4/6/2008
Disposition: DONE
Description: Case Entered
Date Completed: 3/5/2008
Disposition:
Description: Septic Review Complete-U
Date Completed: 7/1/2008
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 4/6/2008
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 7/1/2008
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 7/1/2008
Disposition: DONE
Description: Consistency Review-U
Date Completed: 7/1/2008
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 7/1/2008
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: CONDITIONS
Wording 1. The applicant shall obtain Building Permit from Jefferson County for the structure to house the MBR treatment facility. The application shall address noise containment to meet the standards under JCC 18.30.190. 2. The applicant shall implement the CSWPPP as prepared by Parametrix and dated February 2008. 3. The applicant shall implement design modifications to the utility line installation to meet the standards for flood damage reduction under 15.15.080(1)(c)(i) "All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of flood waters into the system" and (ii) " New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of flood waters into the system and discharges from the system into flood waters." 4. Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit. 5. The applicant shall obtain approval for the State Department of Ecology for an NPDES permit and approval from the State Department of Health for wastewater treatment. 6. The applicant shall meet the standards under JCC 18.30.180 for BMPs in a critical aquifer recharge area either through DOE permitting or meet the standards of 18.30.180 independent of State approval. 7. The applicant shall immediately restore the installation sites to their per-project condition to the maximum extent possible. 8. New utility distribution lines shall be placed underground wherever reasonable and practical. 9. Utilities and transportation facilities shall be installed in the same rights-of-way when the effect will be to reduce the adverse impacts on the physical environment. 10. It shall be the affirmative duty of the applicant who proposes a minor utility development to determine if any state or federal permits or licenses are necessary and then to obtain those permits or licenses at their own expense. 11. Any discharge of sediment-laden runoff or other pollutants to waters of the state is in violation of Chapter 90.48, Water Pollution Control, and WAC 173-201A, Water Quality Standards for Surface Waters of the State of Washington, and is subject to enforcement action. Waters of the state include but are not limited to waters in roadside ditches and storm drains. 12. Erosion control measures must be in place prior to any clearing, grading, or construction. These control measures must be effective to prevent stormwater runoff from carrying soil and other pollutants into surface water or storm drains that lead to waters of the state. Sand, silt, clay particles, and soil will damage aquatic habitat and are considered to be pollutants. 13. Soil in stockpiles should be stabilized or protected with sediment-trapping measures to prevent soil loss. All exposed areas of final grade or areas that are not scheduled for work, whether at final grade or otherwise, shall not remain exposed and un-worked for more than two days, between October 1 and April 30. Between May 1 and September 30, no soils shall remain exposed and un-worked for more than 7 days. 14. Source control best management practices such as plastic covering, mulch, temporary seeding, and phased clearing (for example) should be used to control erosion during construction. More examples of effective source control Best Management Practices can be found in the Washington Department of Ecology's Stormwater Management Manual for Western Washington (2005). 15. During construction, all releases of oils, hydraulic fluids, fuels, other petroleum products, paints, solvents, and other deleterious materials must be contained and removed in a manner that will prevent their discharge to waters and soils of the state. The cleanup of spills should take precedence over other work on the site. 16. A conditional use permit automatically expires and becomes void if the applicant fails to file for a building permit or other necessary development


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-FINDINGS
Wording See Staff Report dated June 3, 2008 and Hearing Examiner Decision dated June 27, 2008 for findings.