Case Number:SDP2007-00061 |
Case Status:Finaled |
Date Received:7/27/2007 |
|
Description:1 YEAR EXTENSION APPROVED 8/29/2009 - Repair of existing decking, decking stringers, bull rails, dock bearing pilings, dolphin pilings, debris wall timbers, pile caps, sewer lines, and sewer hangers, as necessary, to maintain proper dock maintenance and worker safety. Includes repair of roofing and other repairs to existing structures within 200 feet of the shoreline. |
Date Issued:8/29/2007 |
|
Applicant: PORT TOWNSEND PAPER CORP |
Expiration Date:8/29/2009 12:00:00 AM |
|
Site Address:100 PAPER MILL HILL RD |
Case Finaled: |
|
Parcel No:001152006
|
Other Cases |
Parcel Data |
Map It |
|
Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
8/23/2013
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Close case
|
|
Date Completed:
|
| | |
8/23/2013
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Exemption-UF
|
|
Date Completed:
|
| | |
8/29/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Exemption-UF
|
|
Date Completed:
|
| | |
8/29/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print Dummy UDC Permit-UF
|
|
Date Completed:
|
| | |
8/29/2007
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
8/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/1/2007
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
8/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
8/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
8/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
8/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
8/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
8/28/2007
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Other Work/Separate Approval
|
|
Wording
|
| | |
Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.
|
|
|
Title:
|
| | |
Min Use of Hazardous Materials
|
|
Wording
|
| | |
The design, location, and construction of docks, piers, and floats, as well as their subsequent use, shall avoid adverse effects on fish, shellfish, wildlife, marine vegetation, water quality, and hydrogeologic processes. Construction methods shall minimize the use of materials hazardous to the environment.
|
|
|
Title:
|
| | |
Treated Materials Must be Cured
|
|
Wording
|
| | |
All lumber and other materials treated with preservative shall be sufficiently cured to minimize leaching into the water or shore bed, in accordance with the Best Management Practices approved by the Washington Department of Fish and Wildlife.
|
|
|
Title:
|
| | |
Minimize Hazards to Users
|
|
Wording
|
| | |
Docks shall be designed and constructed to minimize hazards to users and to be capable of withstanding the historic extremes of wind, wave, and tides at their location.
|
|
|
Title:
|
| | |
Exempt Maintenance Condition
|
|
Wording
|
| | |
The development shall be essentially the same as the original in location, size, configuration, and external appearance.
|
|
|
Title:
|
| | |
No Fill or Other Material
|
|
Wording
|
| | |
No fill or other material may be placed in the waters or intertidal areas of Jefferson County.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
Comply with HPA
|
|
Wording
|
| | |
In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.
|
|
|
Title:
|
| | |
F-LEGAL NON-CONFORMING
|
|
Wording
|
| | |
The existing docks were constructed prior to January 16, 2001 when the UDC became effective. JCC 18.15.215 states that an existing use may be repaired and maintained without limitation of the ESA section of the UDC.
|
|
|
Title:
|
| | |
F-HPA&CORPS
|
|
Wording
|
| | |
Issues related to over-water develoment activities (including materials, methods, timing, etc.) will be addressed by the Washington Department of Fish and Wildlife HPA and/or U.S. Army Corps of Engineers Section 404 permit.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on August 27, 2007 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review, the following ESAs were confirmed to be present on the subject property: urban shoreline designation, modified shoreline slope stability, seismic hazards, fish and wildlife conservation areas, susceptible aquifer recharge area, and flood hazard.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Geohazard Area
|
|
Wording
|
| | |
Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.
|
|
|
Title:
|
| | |
F-HPA Issued
|
|
Wording
|
| | |
The Washington Department of Fish and Wildlife issued Hydraulic Project Approval (HPA) for this activity on 4/01/04 under Log Number ST-F9382-01.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(3).
|
|
|
Title:
|
| | |
F-APPROVAL FOR SDP ONLY
|
|
Wording
|
| | |
This approval is for a shoreline exemption for dock maintenance and repair only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
F-SDP Exemption Section
|
|
Wording
|
| | |
The Development Review Division finds that this proposal is consistent with Shoreline Master Program JCC Chapter 18.25 and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.
|
|