Permit Case Summary

Case Number: Search Help

Case Number:SDP2007-00016 Case Status:Finaled Date Received:3/13/2007
Description:Shoreline Substantial Development (Secondary Use) Permit and Flood Development Permit for a Bulkhead: This proposal is to reduce the unapproved bulkhead that is in place currently. However, the proposal is an expansion over the legally permitted bulkhead that existed prior to December 2006. The applicant originally applied for a shoreline exemption permit. After an investigative site visit staff determined the project exceeds the threshold for a shoreline exemption permit. This proposal is to reduce the current unapproved bulkhead from 14 ft to 4-ft out from the base. A sinkhole developed near the southeast foundation of the former Oyster House Restaurant and the shore abutment for the pier near the boat ramp for the Trend West Discovery Bay Complex. On February 13, 2007 repair work started without appropriate agency approvals. The new bulkhead could not remain in the footprint of the damaged bulkhead because of soil instability caused by the sinkhole. Projects of this type within a Conservancy Shoreline Designation require a Type III Shoreline Substantial Development permit for a Secondary Use permit with public notice and a public hearing. Other State and local agencies such as the Washington State Dept. of Ecology, Washington Dept. of Fish & Wildlife, Washington Dept. of Natural Resources and Army Corps. Of Engineers have been notified and have had an opportunity to comment on the proposal. A Mitigated Determination of Non-Significance was issued on Tuesday, September 25, 2007. This final determination was issued pursuant to WAC 197-11-355. The SEPA appeal period ended on October 8, 2007. The SEPA Responsible Official did not receive any appeals. Date Issued:10/31/2007
Applicant: DISCOVERY BAY YACHT & RACQUET CLUB Expiration Date:10/31/2009 12:00:00 AM
Site Address:252 ORCAS DR Case Finaled:
Parcel No:901182036 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 2/16/2011
Disposition: DONE
Description: Close case
Date Completed: 1/18/2008
Disposition: DONE
Description: Approve SDP Permit-UF
Date Completed: 10/31/2007
Disposition: DONE
Description: Sent to DOE this date
Date Completed: 10/31/2007
Disposition: DONE
Description: Hearing Examiner Decision
Date Completed: 10/31/2007
Disposition: DONE
Description: Approve SDP Permit-UF
Date Completed: 10/31/2007
Disposition: DONE
Description: Review Complete-U
Date Completed: 10/31/2007
Disposition: DONE
Description: Hearing Exam PH Notice-Pub-UF
Date Completed: 9/21/2007
Disposition: DONE
Description: Hearing Exam PH Notice-APO-UF
Date Completed: 9/21/2007
Disposition: DONE
Description: DRD Reviewer Letter (F)
Date Completed: 8/16/2007
Disposition: DONE
Description: Additional Info Request-U
Date Completed: 8/14/2007
Disposition: DONE
Description: Ntc of App +30-Publish-UF
Date Completed: 6/20/2007
Disposition: DONE
Description: Ntc of App +30-APO-UF
Date Completed: 6/20/2007
Disposition: DONE
Description: Additional Info Request-U
Date Completed: 6/15/2007
Disposition: DONE
Description: Additional Info Request-U
Date Completed: 5/24/2007
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 4/24/2007
Disposition: DONE
Description: Case Entered
Date Completed: 3/16/2007
Disposition:
Description: Septic Review Complete-U
Date Completed: 6/19/2007
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 4/10/2007
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 10/31/2007
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 10/31/2007
Disposition: DONE
Description: Consistency Review-U
Date Completed: 10/31/2007
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 6/19/2007
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: SOIL CONTAMINATION
Wording If contamination of soil or groundwater is readily visible or is revealed by testing the proponent shall contact the Environmental Report Tracking System Coordinator at the Southwest Regional Office at (360)407-6300.

Title: ARCHAEOLOGICAL MONITOR
Wording If heavy equipment is required that may rut the beach surface, or if any excavation is required to remove the rock, the proponent shall hire an archaeological monitor to be present.

Title: BMP'S
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: COMPLY WITH HPA
Wording In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.

Title: RESISTANT TO FLOOD DAMAGE
Wording All materials shall be resistant to flood damage.

Title: MINIMIZE FLOOD DAMAGE
Wording The bulkhead shall be constructed using methods and practices that minimize flood damage.

Title: SUBSTANTIAL COMPLIANCE
Wording Construction shall be in substantial compliance with the plans submitted to Jefferson County during the permit process as they exist now or are hereafter amended by Jefferson County and/or the Washington State Department of Ecology.

Title: PROPER DISPOSAL
Wording Proper disposal of construction debris must be on land in such a manner that debris cannot enter the water body or cause water quality degradation of state waters.

Title: SEPARATE APPROVAL
Wording Work within the jurisdiction of the Shoreline Program other than as described above shall receive separate review from Jefferson County Department of Community Development.

Title: CONTACT JEFF CO
Wording Prior to construction, the proponent shall contact the Jefferson County Department of Community Development at (360)385-9406 with estimated timelines for monitoring and plan compliance.