Permit Case Summary

Case Number: Search Help

Case Number:SDP2004-00039 Case Status:Finaled Date Received:8/16/2004
Description:Shoreline Exemption - To replace a single pile and stringer section associated with an existing dock. Date Issued:8/18/2004
Applicant: PORT HADLOCK/K S C LLC Expiration Date:8/18/2005 12:00:00 AM
Site Address:310 HADLOCK BAY RD Case Finaled:
Parcel No:901014007 Other Cases Parcel Data Map It Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 1/26/2006
Disposition: DONE
Description: Close case
Date Completed: 9/13/2004
Disposition: DONE
Description: Approve Exemption-UF
Date Completed: 8/18/2004
Disposition: DONE
Description: Review Complete-U
Date Completed: 8/18/2004
Disposition: DONE
Description: Application Received-UF
Date Completed: 8/16/2004
Disposition: DONE
Description: Case Entered
Date Completed: 8/16/2004
Disposition:
Description: App Substantially Complete-U
Date Completed: 8/18/2004
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 8/18/2004
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 8/18/2004
Disposition: DONE
Description: Consistency Review-U
Date Completed: 8/18/2004
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 8/18/2004
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.

Title: Treated Materials Must be Cured
Wording All lumber and other materials treated with preservative shall be sufficiently cured to minimize leaching into the water or shore bed, in accordance with the Best Management Practices approved by the Washington Department of Fish and Wildlife.

Title: Site Plan
Wording Construction shall be in substantial compliance with the site plan submitted on August 13, 2004 as it exists now or is hereafter amended by Jefferson County and/or the Washington Department of Ecology.

Title: Exempt Maintenance Condition
Wording The development shall be essentially the same as the original in location, size, configuration, and external appearance.

Title: No Fill or Other Material
Wording No fill or other material may be placed in the waters or intertidal areas of Jefferson County.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: Hydraulic Code/HPA Check
Wording Prior to commencing development activity, proponent is responsible for informing the Washington Department of Fish and Wildlife (WDFW) in order for WDFW to determine whether this action is subject to the Washington State Hydraulic Code (Chapter 220-10 WAC). Hydraulic Project Approval (HPA) is required for all hydraulic projects, which are defined as construction or performance of other work that will use, divert, obstruct, or change the natural flow or bed of any of the salt or fresh waters of the state.

Title: Comply with HPA
Wording In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.

Title: Army Corps Check
Wording Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on August 18, 2004 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Fish and Wildlife Habitat Areas (over marine waters) and stormwater.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800((3) - Repair and Maintenance Activities.

Title: F-Site Plan Changes
Wording The site plan as submitted with the shoreline exemption application (SDP 04-39) on has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated August 18, 2004 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-Approval for _____ Only
Wording This approval is for the replacement of a single pile and stringer section associated with an existing dock only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: F-HPA & CORP. OF ENGINEERS PERMIT
Wording Issues related to over-water development activities (including materials, methods, timing, etc.) will be addressed by the WA State Department of Fish and Wildlife HPA and/or Corp of Engineers Permit.

Title: F-SDP Exemption Section
Wording The Development Review Division finds that this proposal is consistent with Shoreline Master Program Section 3.402.(6) and is consequently exempt from the substantial development permit (SDP) requirements. Exemptions from the substantial development permit requirements do not exempt a proposed development from compliance with the applicable policies and standards of the Shoreline Master Program or other applicable Federal, State, or local permit or license requirements.