Permit Case Summary

Case Number: Search Help

Case Number:SDP2000-10019 Case Status:Finaled Date Received:10/10/2000
Description:This application is for the placement of a recreational mooring buoy in Scow Bay, Kilisut Harbor, Marrowstone Island. The application states that no other mooring buoys are located within 100 feet of the proposed coordinates. Other permitting agencies involved include the Washington Dept. of Fish and Wildlife, the Washington Dept. of Natural Resources, and the US Army Corps of Engineers. The proposal is exempt from review under the State Environmental Policy Act pursuant to WAC 197-11-800(25)(g). Date Issued:5/30/2001
Applicant:BRAD CLINEFELTER Expiration Date:5/30/2003 12:00:00 AM
Site Address: BLANK PARCEL FILE Case Finaled:
Parcel No:KILISUTHARBOR Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 8/27/2003
Disposition: DONE
Description: Close case
Date Completed: 5/30/2003
Disposition: DONE
Description: TYPE A Appeal Instrctns (F)
Date Completed: 5/30/2001
Disposition: DONE
Description: Issue SDP Permit
Date Completed: 5/30/2001
Disposition: DONE
Description: Additional Information Request
Date Completed: 5/10/2001
Disposition: DONE
Description: Pub Date in Leader-Ntc of Appl
Date Completed: 10/18/2000
Disposition: DONE
Description: App Substantially Complete (F)
Date Completed: 10/11/2000
Disposition: DONE
Description: (F) SDP Application Notice +30
Date Completed: 10/11/2000
Disposition: DONE
Description: Case Entered
Date Completed: 10/10/2000
Disposition:
Description: Shoreline Planner Review
Date Completed: 5/30/2001
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Buoy: No More Than Two (2) Boats
Wording No more than two (2) boats shall be secured by a mooring buoy.

Title: Buoy marked
Wording The buoy shall be permanently marked with the proponent's name, address, and telephone number and the permit number.

Title: Buoy Placement-SDP
Wording The buoy shall be placed a minimum of 100 feet from existing permitted or exempted adjacent mooring buoys, docks, and piers. The buoy shall be located at least 100 feet seaward of the minus 6 foot mean lower low water tidal elevation.

Title: Vessel maintenance activities
Wording Vessel maintenance activities which may cause water pollution, including hull chipping and painting, shall be performed at designated facilities.

Title: Buoy Permission Only
Wording This permit constitutes permission to place a mooring buoy and ground tackle only. Permission to place floats is not authorized.

Title: Buoy discernible from a distance
Wording The buoy shall be discernible from a minimum distance of 100 yards under normal daylight conditions.

Title: Discharge oil: state & fed regs
Wording The proponents shall comply with all relevant state and federal regulations pertaining to the discharge of oil.

Title: Notification Prior to Beginning
Wording The proponent shall notify the Jefferson County Department of Community Development at (360) 379-4450 forty-eight (48) hours prior to commencing construction in order to allow monitoring and ensure compliance with permit conditions.

Title: Other Work/Separate Approval
Wording Work within the jurisdiction of the Shoreline Master Program other than as described above shall receive separate review from this Department.

Title: Progress towards completion
Wording Substantial progress towards completion of the project shall be performed within two years of the issuance of the permit.

Title: Comply with HPA
Wording In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.

Title: Army Corps Check
Wording Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-HPA Issued
Wording The Washington Department of Fish and Wildlife issued Hydraulic Project Approval (HPA) for this activity on May 7, 2001 under Log Number 00-E7814-01. The HPA expires on January 2, 2002.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-800-11(25)(g).