Title:
|
| | |
PERMIT ON SITE
|
|
Wording
|
| | |
This permit must be located on site when any work encompassed by the permit is being performed. Failure to do so may result in suspension of all work.
|
|
|
Title:
|
| | |
CULVERT 12"
|
|
Wording
|
| | |
A minimum 12 inch diameter culvert, not to exceed 60 feet in length, to accommodate a 20 foot wide driveway with 35 foot approach radius is required. If more than one culvert is used, both culverts must be made of the same material and be connected with an approved band. The apron shall be paved (see attached).
|
|
|
Title:
|
| | |
SIGHT BRUSHING
|
|
Wording
|
| | |
The applicant shall be responsible for maintaining all vegetation to provide for the adequate sight distance adjacent to this road approach.
|
|
|
Title:
|
| | |
RESPONSIBLE
|
|
Wording
|
| | |
The applicant shall be responsible for the cost to repair any and all damage to the county roadway and rights-of-way, including the integrity of all survey monuments or boundary markers.
|
|
|
Title:
|
| | |
CRUSHED SURFACING
|
|
Wording
|
| | |
The applicant must place a minimum of 3 inches of crushed rock per WSDOT Standard Spec 9-03.9(3), starting from the edge of the road and extending back a minimum of 20 feet for the full width of the access and its radius. The approach must be finished with a minimum of 3" of asphalt for the full width of the approach, including radius, to the right-of-way line, or 20', whichever is greater. The access and installation of the crushed rock surfacing material and asphalt apron shall not impact the existing grade of the county road shoulder.
|
|
|
Title:
|
| | |
CONSTR APPROACH
|
|
Wording
|
| | |
The applicant shall be responsible for maintaining a stabilized construction entrance, which shall be constructed as follows: 4 inch to 8 inch quarry spalls a minimum of 12 inches deep, a minimum width of 20 feet, a minimum radius of 25 feet, and a minimum length of 100 feet from the county road. The applicant shall also be responsible for immediately removing any material spilled or tracked onto the county road.
|
|
|
Title:
|
| | |
SURFACE WATER
|
|
Wording
|
| | |
The grade of the approach shall follow the crown of the road to the ditch, and be such that all surface water shall be directed into a ditch line and not onto the county road. The applicant shall contact Jefferson County Public Works (360-385-9160) for a final grade inspection prior to completing the driveway.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
It is recommended that the approach be built so the driveway is on the platted centerline of the private right-of-way of Thomas Ave.
|
|
|
Title:
|
| | |
RAP ONLY
|
|
Wording
|
| | |
This approval is for a road approach only and does not constitute approval of other activities within the right of way or on this parcel. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
PRE-CON
|
|
Wording
|
| | |
Applicant must give Jefferson County Public Works office (360-385-9159) a minimum of 7 working days notice prior to beginning work. An on-site pre-construction conference shall be scheduled by the applicant and will include Public Works and the contractor who will be performing the work. Prior to this meeting, any utility locate marks shall be done (Call 811-48 hours before you dig).
|
|
|
Title:
|
| | |
FINAL INSPECTION
|
|
Wording
|
| | |
The Applicant must contact the Public Works Department for a final inspection upon completion of the installation.
|
|