Title:
|
| | |
PERMIT ON SITE
|
|
Wording
|
| | |
This permit must be located on site when any work encompassed by the permit is being performed. Failure to do so may result in suspension of all work.
|
|
|
Title:
|
| | |
RESPONSIBLE
|
|
Wording
|
| | |
The applicant shall be responsible for the cost to repair any and all damage to the county roadway and rights-of-way, including the integrity of all survey monuments or boundary markers.
|
|
|
Title:
|
| | |
NO CULVERT
|
|
Wording
|
| | |
Approach culverts are not necessary at these locations at this time. Each access must accommodate a 20 foot wide driveway with a 25 foot approach radius.
|
|
|
Title:
|
| | |
CONSTR APPROACH
|
|
Wording
|
| | |
The applicant shall be responsible for maintaining a stabilized construction entrance, which shall be constructed as follows: 4 inch to 8 inch quarry spalls a minimum of 12 inches deep, a minimum width of 20 feet, a minimum radius of 25 feet, and a minimum length of 100 feet from the county road. The applicant shall also be responsible for immediately removing any material spilled or tracked onto the county road.
|
|
|
Title:
|
| | |
SURFACE WATER
|
|
Wording
|
| | |
The grade of each approach shall follow the crown of the road to the back of the shoulder area, and be such that no surface water is directed onto the county road. The approaches shall be graded so rock does not spill out onto the roadway and, if so, shall be cleaned up as soon as possible.
|
|
|
Title:
|
| | |
CUSTOM CONDITION
|
|
Wording
|
| | |
All temporary approaches must be removed and the right-of-way restored to its pre-existing condition.
|
|
|
Title:
|
| | |
SIGNS
|
|
Wording
|
| | |
Signs indicating logging activity/trucks entering the roadway must be posted at each location on each side of the approach.
|
|
|
Title:
|
| | |
TREE REMOVAL
|
|
Wording
|
| | |
The Applicant has permission to remove the trees within the right-of-way, adjacent to their parcel. All work shall be done from within the parcel and back side of the right of way.
|
|
|
Title:
|
| | |
RAP ONLY
|
|
Wording
|
| | |
This approval is for these four logging approaches only and does not constitute approval of other activities within the right of way or on this parcel. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
PRE-CON
|
|
Wording
|
| | |
Applicant must give Jefferson County Public Works office (360-385-9159) a minimum of 7 working days notice prior to beginning work. An on-site pre-construction conference shall be scheduled by the applicant and will include Public Works and the contractor who will be performing the work. Prior to this meeting, any utility locate marks shall be done (Call 811-48 hours before you dig).
|
|
|
Title:
|
| | |
FINAL INSPECTION
|
|
Wording
|
| | |
The Applicant must contact the Public Works Department for a final inspection upon completion of all conditions of this permit.
|
|