Title:
|
| | |
PERMIT ON SITE
|
|
Wording
|
| | |
This permit must be located on site when any work encompassed by the permit is being performed. Failure to do so may result in suspension of all work.
|
|
|
Title:
|
| | |
CULVERT 12"
|
|
Wording
|
| | |
A minimum 12 inch diameter culvert, not to exceed 40 feet in length, to accommodate a 16 foot wide driveway with 15-25 foot approach radius is required. If more than one culvert is used, both culverts must be made of the same material and be connected with an approved band (see attached)
|
|
|
Title:
|
| | |
SIGHT BRUSHING
|
|
Wording
|
| | |
The applicant shall be responsible for maintaining all vegetation to provide for the adequate sight distance adjacent to this road approach.
|
|
|
Title:
|
| | |
RESPONSIBLE
|
|
Wording
|
| | |
The applicant shall be responsible for the cost to repair any and all damage to the county roadway and rights-of-way, including the integrity of all survey monuments or boundary markers.
|
|
|
Title:
|
| | |
NO CULVERT
|
|
Wording
|
| | |
An approach culvert is not necessary the approaches at mile post 3.015 left and mile post 3.086 left at this time. The access must accommodate a 16 foot wide driveway with a 15-25 foot approach radius.
|
|
|
Title:
|
| | |
CONSTR APPROACH
|
|
Wording
|
| | |
The applicant shall be responsible for maintaining a stabilized construction entrance, which shall be constructed as follows: 4 inch to 8 inch quarry spalls a minimum of 12 inches deep, a minimum width of 20 feet, a minimum radius of 25 feet, and a minimum length of 100 feet from the county road. The applicant shall also be responsible for immediately removing any material spilled or tracked onto the county road.
|
|
|
Title:
|
| | |
WORKER/ROW
|
|
Wording
|
| | |
Any time that workers are on the county right-of-way warning signs shall be posted that workers are present. All workers shall comply with applicable Labor and Industries Guidelines for clothing including reflective vests. Any time that equipment must enter onto the right-of-way, signing and flaggers shall be used in accordance with applicable MUTCD standards.
|
|
|
Title:
|
| | |
TREE REMOVAL
|
|
Wording
|
| | |
The Applicant has permission to remove the trees within the right-of-way, adjacent to their parcel. All work shall be done from within the parcel and back side of the right of way.
|
|
|
Title:
|
| | |
PRE-CON
|
|
Wording
|
| | |
Applicant must give Jefferson County Public Works office (360-385-9159) a minimum of 7 working days notice prior to beginning work. An on-site pre-construction conference shall be scheduled by the applicant and will include Public Works and the contractor who will be performing the work. Prior to this meeting, any utility locate marks shall be done (Call 811-48 hours before you dig).
|
|