Description:
|
| | |
Cancel Permit
|
|
Date Completed:
|
| | |
9/4/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Inspection/Conditions Not Met
|
|
Date Completed:
|
| | |
9/4/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Attached Document
|
|
Date Completed:
|
| | |
7/23/2018
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Inspection/Conditions Not Met
|
|
Date Completed:
|
| | |
9/4/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Permit
|
|
Date Completed:
|
| | |
3/10/2011
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print ESA Review Form-F
|
|
Date Completed:
|
| | |
2/16/2011
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
2/16/2011
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
3/9/2011
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
3/9/2011
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
3/9/2011
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
NO CULVERT
|
|
Wording
|
| | |
An approach culvert is not necessary at the access to the Applicant's parcel at this time; however, if drainage becomes a problem here in the future the county reserves the right to require one. The access shall accommodate a 10-16 foot wide driveway with a 10-25 foot approach radius.
|
|
|
Title:
|
| | |
NO PROTEST AGREEMENT
|
|
Wording
|
| | |
A No Protest Agreement was signed and recorded March 1, 2011 under AFN 558412 which pertains to the right of way adjoining the parcel as it is presently indentified; Tract 68 of Seventh Avene Acre Tracts, Vol. 1, Pg 127, Jefferson County, WA. The right of way is that portion of Foster St adjoining parcels 994200008, 994200006, 994200016 & 994200005. The Agreement stipulates that the owner will not protest future development of this portion of platted Foster St. or the associated cost sharing of constructing these improvements and appurtenances.
|
|
|
Title:
|
| | |
SURVEY
|
|
Wording
|
| | |
The right of way shall be located and staked by a surveyor licensed in the State of Washington.
|
|
|
Title:
|
| | |
BUILD ON CENTERLINE
|
|
Wording
|
| | |
The road shall be built on the centerline within the platted right of known as Foster St. adjoining parcels 994200008, 994200006, 994200016 & 994200005, all within the Plat of Seventh Avenue Acre Tracts, Vol 1, Pg 127. The road shall be build in accordance with the attached Road Standard for Private Roads.
|
|
|
Title:
|
| | |
NON-EXCLUSIVE USE
|
|
Wording
|
| | |
Nothing contained herein shall be construed that the County is relinquishing any public rights to said right of way. Furthermore, the Applicant acknowledges that this right of way was dedicated to the public forever as described in the Seventh Avenue Acre Plat recorded under Volume 1, Page 127, Jefferson County, WA. Therefore, the public cannot be barred from said right of way.
|
|
|
Title:
|
| | |
PRE-CON
|
|
Wording
|
| | |
Applicant must give Jefferson County Public Works office (360-385-9160) a minimum of 7 working days notice prior to beginning work. An on-site pre-construction conference shall be scheduled by the applicant and will include Public Works and the contractor who will be performing the work.
|
|
|
Title:
|
| | |
FINAL INSPECTION
|
|
Wording
|
| | |
The Applicant must contact Jefferson County Public Works for inspections of the following:
a. Survey markers showing right of way limits or centerline.
b. Clearing limits
c. Subgrade
d. Gravel base
e. Top course
All inspections must be done prior to a final building inspection. Upon approval of the final inspection, any and all maintenance of this 'driveway' shall be the responsibility of the users of the right of way. Jefferson County will have no obligations for maintenance activities, included, but not limited to, drainage, grading, brushing, mowing, ditching or adding surface material.
|
|