Description:
|
| | |
Final Inspection Approval
|
|
Date Completed:
|
| | |
11/27/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Permit
|
|
Date Completed:
|
| | |
9/4/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Loc Approved for SPAAD "I"
|
|
Date Completed:
|
| | |
4/22/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print ESA Review Form-F
|
|
Date Completed:
|
| | |
10/26/2009
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
10/26/2009
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
4/22/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
4/22/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
4/22/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
4/22/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
PERMIT ON SITE
|
|
Wording
|
| | |
This permit must be located on site when any work encompassed by the permit is being performed. Failure to do so may result in suspension of all work.
|
|
|
Title:
|
| | |
SIGHT BRUSHING
|
|
Wording
|
| | |
The applicant shall be responsible for maintaining all vegetation on their property to maintain the minimum sight distance requirement for this location.
|
|
|
Title:
|
| | |
RESPONSIBLE
|
|
Wording
|
| | |
The applicant shall be responsible for the cost to repair any and all damage to the county roadway and rights-of-way, including the integrity of all survey monuments or boundary markers.
|
|
|
Title:
|
| | |
NO CULVERT
|
|
Wording
|
| | |
The access shall accommodate a 10 to 16 foot wide driveway with 10-25 foot approach radius. An approach culvert is not necessary at this location at this time; however, if drainage becomes a problem here in the future the county reserves the right to require one.
|
|
|
Title:
|
| | |
CRUSHED SURFACING
|
|
Wording
|
| | |
The applicant must place a minimum of 2 inches of crushed surfacing to the right- of-way line.
|
|
|
Title:
|
| | |
SURFACE WATER
|
|
Wording
|
| | |
The grade of the approach shall be such that no surface water is directed onto the county road.
|
|
|
Title:
|
| | |
PRE-CON
|
|
Wording
|
| | |
Applicant must give Jefferson County Public Works office (360-385-9159) a minimum of 7 working days notice prior to beginning work. An on-site pre-construction conference shall be scheduled by the applicant and will include Public Works and the contractor who will be performing the work. Prior to this meeting, any utility locate marks shall be done (Call 811-48 hours before you dig).
|
|
|
Title:
|
| | |
FINAL INSPECTION
|
|
Wording
|
| | |
The Applicant must contact the Public Works Department at 360-385-9159 for a final inspection prior to a final building inspection.
|
|