Description:
|
| | |
Final Inspection Approval
|
|
Date Completed:
|
| | |
5/10/2010
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Permit
|
|
Date Completed:
|
| | |
2/8/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print ESA Review Form-F
|
|
Date Completed:
|
| | |
2/4/2008
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
2/4/2008
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
2/8/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
2/8/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
2/8/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
2/8/2008
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
SIGHT BRUSHING
|
|
Wording
|
| | |
The applicant shall be responsible for maintaining all vegetation on their property to maintain the minimum sight distance requirement for this location.
|
|
|
Title:
|
| | |
NO CULVERT
|
|
Wording
|
| | |
The approach shall accommodate a 10 to 16 foot wide driveway with 10-25 foot approach radius. An approach culvert is not necessary at this location at this time; however, if drainage becomes a problem here in the future the county reserves the right to require one.
|
|
|
Title:
|
| | |
CRUSHED SURFACING
|
|
Wording
|
| | |
The applicant must place a minimum of 2 inches of crushed surfacing to the right- of-way line.
|
|
|
Title:
|
| | |
SURFACE WATER
|
|
Wording
|
| | |
The grade of the approach shall be such that no surface water is directed onto the county road.
|
|
|
Title:
|
| | |
ESA
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Aquifer Recharge Area (SARPA-Susceptible Aquifer Recharge Protection Area).
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
RAP ONLY
|
|
Wording
|
| | |
This approval is for a road approach only and does not constitute approval of other activities within the right of way or on this parcel. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
FINAL INSPECTION
|
|
Wording
|
| | |
The Applicant must contact the Public Works Department for a final inspection upon completion of installation.
|
|