Case Number:RAP2002-00053 Case Status:Canceled Date Received:3/26/2002
Description:ROAD APPROACH & 911 - CEDAR AVE Date Issued:4/15/2002
Applicant:GERTRUDE ADAMS Expiration Date:4/15/2003 12:00:00 AM
Site Address:91 CEDAR AVE Case Finaled:6/19/2002
Parcel No:956701002 Other Cases Parcel Data Map It

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Cancel Permit
Date Completed: 6/19/2002
Disposition: DONE
Description: Issue Permit
Date Completed: 4/15/2002
Disposition: DONE
Description: Review Complete-U
Date Completed: 4/10/2002
Disposition: DONE
Description: Case Entered
Date Completed: 3/27/2002
Disposition:
Description: App Substantially Complete-U
Date Completed: 4/2/2002
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 4/3/2002
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 4/3/2002
Disposition: DONE
Description: Consistency Review-U
Date Completed: 4/10/2002
Disposition: DONE
Description: Print ESA Review Form-F
Date Completed: 3/27/2002
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: NO CULVERT
Wording An approach culvert is not necessary at this location at this time; however, if drainage becomes a problem here in the future the county reserves the right to require one.

Title: CRUSHED SURFACING
Wording The applicant must place a minimum of 2 inches of crushed surfacing to the right- of-way line.

Title: SURFACE WATER
Wording The grade of the approach shall be such that all surface water shall not be directed onto the county road.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: P-PRIVATE ROAD APPROACH
Wording The applicant may install a private road approach to Cedar Ave. at mile post .09 left.