Description:
|
| | |
Certificate of Occupancy-F
|
|
Date Completed:
|
| | |
10/24/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
10/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Blocking & Tie Down
|
|
Date Completed:
|
| | |
9/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
8/3/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
8/1/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
10/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Smoke & CO
|
|
Date Completed:
|
| | |
10/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Skirting & Ventilation
|
|
Date Completed:
|
| | |
10/4/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Blocking & Tie Down
|
|
Date Completed:
|
| | |
9/16/2022
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Insp - MH Foundation
|
|
Date Completed:
|
| | |
8/17/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Erosion Control
|
|
Date Completed:
|
| | |
10/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
8/17/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Address Posted
|
|
Date Completed:
|
| | |
10/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
8/1/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
8/1/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Erosion Control
|
|
Date Completed:
|
| | |
10/19/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic System Finaled
|
|
Date Completed:
|
| | |
10/1/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
8/1/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
6/23/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
8/1/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
7/18/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
6/13/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
7/18/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
7/29/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval
|
|
Date Completed:
|
| | |
8/2/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
8/1/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
7/18/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
6/9/2022
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
APPROVAL
|
|
Wording
|
| | |
This approval is for a new manufactured home only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the manufactured home application on June 9, 2022 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated July 18, 2022 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
CRITICAL AREAS
|
|
Wording
|
| | |
The Geographic Information Systems mapping review identified the following Critical Areas on the subject property: CARA - SARPA
|
|
|
Title:
|
| | |
BMPS
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
SMALL STORMWATER
|
|
Wording
|
| | |
The applicant is proposing to create or add 1054 square feet of impervious surface and 1900 square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require your proposal comply with Minimum Requirement #2 (Construction Stormwater Pollution Prevention) of the Department of Ecology Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
NO PROTEST
|
|
Wording
|
| | |
A Irondale/Hadlock Sanitary Sewer System No Protest Agreement has been recorded under AFN 655392 on July 29, 2022.
|
|
|
Title:
|
| | |
Water line/Septic system setback
|
|
Wording
|
| | |
10' minimum separation required between the water line and any onsite sewage system components including sewage transport lines.
|
|
|
Title:
|
| | |
SEPTIC - No Assurance future dev.
|
|
Wording
|
| | |
Approval of this permit does not provide any assurance of future approvals for onsite sewage disposal on the property or use of any existing septic systems. Actions taken to date and proposed as part of this project may limit or prevent future development of an onsite sewage system. Future proposals must meet current code at the time of application.
|
|
|
Title:
|
| | |
Septic - Stormwater setbacks
|
|
Wording
|
| | |
SEPTIC SYSTEM COMPONENT SETBACKS TO STORMWATER MANAGEMENT FACILITIES -
Any interceptor/curtain drain or foundation drain, or any other source of water that is downgradient or below MUST be setback a minimum of 30’ from any septic system dispersal area (drainfield) and 5’ from any septic tanks.
Splash blocks must be directed away from ALL septic components.
|
|