Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
8/3/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
8/3/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Inspection Reminder Sent (1st)
|
|
Date Completed:
|
| | |
6/27/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
7/29/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Erosion Control
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Erosion Control
|
|
Date Completed:
|
| | |
9/15/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
7/27/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
7/27/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Address Posted
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Skirting & Ventilation
|
|
Date Completed:
|
| | |
9/6/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Blocking & Tie Down
|
|
Date Completed:
|
| | |
7/14/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - MH Foundation
|
|
Date Completed:
|
| | |
8/13/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
8/13/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Address Posted
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
4/28/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic System Finaled
|
|
Date Completed:
|
| | |
1/13/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
4/21/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
7/12/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
7/28/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
7/27/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
7/27/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
4/21/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
5/14/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval
|
|
Date Completed:
|
| | |
5/26/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
6/1/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
4/21/2021
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
APPROVAL FOR MANUFACTURED ONLY
|
|
Wording
|
| | |
This APPROVAL is for a New Manufactured Home only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the New Manufactured Home application on April 28th, 2021 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated July 27th, 2021 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
CRITICAL AREAS
|
|
Wording
|
| | |
The Geographic Information Systems mapping review identified the following Critical Areas on the subject property: Special Aquifer Recharge Area
|
|
|
Title:
|
| | |
AQUIFER RECHARGE AREA
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County. Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
BMPS
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
MEDIUM STORMWATER
|
|
Wording
|
| | |
The applicant is proposing to create or add 2,005 square feet of impervious surface and 2,005 square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require the project applicant submit a stormwater plan meeting Minimum Requirements #1 through #5 of the Department of Ecology Stormwater Management Manual for Western Washington.
|
|
|
Title:
|
| | |
STORMWATER PLAN
|
|
Wording
|
| | |
A Stormwater Plan has been submitted and approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed.
|
|
|
Title:
|
| | |
FULL INFILTRATION
|
|
Wording
|
| | |
The applicant has proposed and been approved to utilize downspout full infiltration to manage stormwater from roof areas. The soils were evaluated by using the septic soil logs and found to have three or more feet of permeable soils and the anticipated water table is at least 1 foot below the bottom of the proposed drywell.The drywell will be designed per the requirements of the Stormwater Management Manual for Western Washington BMP T5.10A. 5 ft x 4 ft x 12 ft Drywell (Gravel Drain).
|
|
|
Title:
|
| | |
SHEET FLOW DISPERSION
|
|
Wording
|
| | |
The applicant has proposed and been approved to utilize BMP T5.12: sheet flow dispersion for driveway stormwater management. Stormwater shall drain into the infiltration basin located in the roadway. The sheet flow shall be designed per the requirements of the stormwater manual.
|
|
|
Title:
|
| | |
SILT FENCE
|
|
Wording
|
| | |
Silt fencing shall be installed prior to beginning any ground-disturbing activities on the property.
|
|
|
Title:
|
| | |
NO PROTEST AGREEMENT
|
|
Wording
|
| | |
Parcel 971900036 is located in an Urban Growth Area (Irondale - Port Hadlock UGA). An Irondale/Hadlock Sanitary Sewer System No Protest Agreement has been recorded on November 10th, 2008 under AFN 538595 for the purpose of property owner agreement not to protest a future LID or other pro rata sharing of costs to construct and extend public sewer to the property, as part of the urban level of service phasing plan in the capital facilities plan for the UGA.
|
|
|
Title:
|
| | |
PLANNER
|
|
Wording
|
| | |
AH
|
|