Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
7/27/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Inspection Reminder Sent (1st)
|
|
Date Completed:
|
| | |
6/27/2022
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
8/4/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
7/27/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
7/27/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Ext. Shear Wall Nailing
|
|
Date Completed:
|
| | |
11/2/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Straps (hold downs)
|
|
Date Completed:
|
| | |
7/27/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Foundation Stem Wall
|
|
Date Completed:
|
| | |
10/22/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
9/24/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
9/24/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
4/28/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic System Finaled
|
|
Date Completed:
|
| | |
1/13/2022
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
4/21/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
7/12/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
8/3/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
8/3/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
8/3/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
4/21/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
5/24/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
6/1/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
4/20/2021
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
C- APPROVAL FOR
|
|
Wording
|
| | |
This approval is for a detached garage with no plumbing or heat only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
C- SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the building permit application on April 13, 2021 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated August 3, 2021 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
C- CRITICAL AREAS
|
|
Wording
|
| | |
The Geographic Information Systems mapping review identified the following Critical Areas on the subject property: CARA SARPA designation.
|
|
|
Title:
|
| | |
C- CRITICAL AQUIFER RECHARGE AREA
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County. Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
C- STORMWATER BMPS
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
C- SMALL STORMWATER PROJECT
|
|
Wording
|
| | |
The applicant is proposing to create or add 528 square feet of impervious surface and 528 square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require your proposal comply with Minimum Requirement #2 (Construction Stormwater Pollution Prevention) of the Department of Ecology Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems. This project's stormwater management methods will integrate with the stormwater controls of BLD2021-00236
|
|