Description:
|
| | |
CANCEL BUILDING PERMIT
|
|
Date Completed:
|
| | |
2/16/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
5/21/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Erosion Control
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Erosion Control
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Ext. Shear Wall Nailing
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Straps (hold downs)
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Footing Drains
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Foundation Stem Wall
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Erosion Control
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
4/17/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic System Finaled
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
4/15/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
5/5/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
5/5/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
5/5/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
5/5/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
4/17/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
4/17/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
4/22/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
4/15/2020
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
APPROVAL FOR GARAGE ONLY
|
|
Wording
|
| | |
This approval is for a new detached garage only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the detached garage application on April 14, 2020 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated May 5, 2020 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
CRITICAL AREAS
|
|
Wording
|
| | |
The Geographic Information Systems mapping review identified the following Critical Areas on the subject property: Critical Aquifer Recharge Area
|
|
|
Title:
|
| | |
CARA
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County. Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
BMPS
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
MEDIUM STORMWATER
|
|
Wording
|
| | |
The applicant is proposing to create or add 2252 square feet of impervious surface and 2252 square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require the project applicant submit a stormwater plan meeting Minimum Requirements #1 through #5 of the Department of Ecology Stormwater Management Manual for Western Washington. The stormwater plan shall address measures to control stormwater, erosion and sediment during construction and shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
STORMWATER PLAN
|
|
Wording
|
| | |
A Stormwater Plan has been submitted and approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed.
|
|
|
Title:
|
| | |
DRYWELL
|
|
Wording
|
| | |
The applicant has proposed and been approved to utilize downspout full infiltration to manage stormwater from roof areas. The soils were evaluated by using the septic soil logs and found to have three or more feet of permeable soils and the anticipated water table is at least 1 foot below the bottom of the proposed drywell. The drywell will be designed per the requirements of the Stormwater Management Manual for Western Washington BMP T5.10. The drywell shall be 5 x 12 x 4 cubic feet.
|
|
|
Title:
|
| | |
SHEET FLOW
|
|
Wording
|
| | |
The applicant has proposed and been approved to utilize sheet flow dispersion for driveway stormwater management. The sheet flow shall be designed per the requirements of the stormwater manual. A 2-foot wide gravel transition zone and 10-feet of vegetated flow path are required.
|
|
|
Title:
|
| | |
PLANNER
|
|
Wording
|
| | |
SCC
|
|
|
Title:
|
| | |
NO PLUMBING REVWD OR APPRVD
|
|
Wording
|
| | |
No plumbing has been reviewed or approved for this project by Jefferson County Public Health. Additional requirements may apply if plumbing is proposed.
|
|