Permit Case Summary

Case Number: Search Help

Case Number:BLD2019-00125 Case Status:Finaled Date Received:4/4/2019
Description:NEW MANUFACTURED HOME Date Issued:6/3/2019
Applicant: STO LLC Expiration Date:6/3/2020 12:00:00 AM
Site Address:144 SUNSET MEADOWS LN Case Finaled:4/17/2020
Parcel No:971900037 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 5/7/2020
Disposition:
Description: Insp - FINAL FINAL Building
Date Completed: 4/17/2020
Disposition: DONE
Description: Insp - Final Building
Date Completed: 4/17/2020
Disposition: DONE
Description: Updated/Add'l Info Recv'd
Date Completed: 4/16/2020
Disposition: DONE
Description: Insp Reminder (1st - non bldg)
Date Completed: 6/30/2020
Disposition:
Description: Updated/Add'l Info Recv'd
Date Completed: 11/15/2019
Disposition: DONE
Description: Updated/Add'l Info Recv'd
Date Completed: 11/14/2019
Disposition:
Description: Insp - Foundation Footing
Date Completed: 11/14/2019
Disposition: DONE
Description: Insp - Setbacks
Date Completed: 11/14/2019
Disposition: DONE
Description: Insp - Footing Drains
Date Completed: 11/5/2019
Disposition: DONE
Description: Insp - Skirting & Ventilation
Date Completed: 11/5/2019
Disposition: DONE
Description: Insp - Blocking & Tie Down
Date Completed: 10/22/2019
Disposition: DONE
Description: Insp - MH Foundation
Date Completed: 10/1/2019
Disposition: DONE
Description: Insp - Erosion Control
Date Completed: 10/1/2019
Disposition: DONE
Description: Insp - Setbacks
Date Completed: 10/1/2019
Disposition: DONE
Description: Issue Mobile Home Permit (F)
Date Completed: 6/3/2019
Disposition: DONE
Description: Final Planning Approval
Date Completed: 4/17/2020
Disposition: DONE
Description: Updated/Add'l Info Recv'd
Date Completed: 5/6/2019
Disposition: DONE
Description: A Clock Interrupt
Date Completed: 5/14/2019
Disposition: DONE
Description: Additional Info Request-DRD
Date Completed: 5/14/2019
Disposition: DONE
Description: Building Permit Application(F)
Date Completed: 4/4/2019
Disposition: DONE
Description: Septic System Finaled
Date Completed: 4/14/2020
Disposition: DONE
Description: Address Review Complete
Date Completed: 4/4/2019
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 4/4/2019
Disposition: DONE
Description: Consistency Review-U
Date Completed: 5/14/2019
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 5/14/2019
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 5/14/2019
Disposition: DONE
Description: Contractor License/Bond Info
Date Completed: 4/4/2019
Disposition: DONE
Description: Potable Water Approval
Date Completed: 4/30/2019
Disposition: DONE
Description: Septic Review Complete-U
Date Completed: 6/1/2019
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 5/14/2019
Disposition: DONE
Description: Case Entered
Date Completed: 4/4/2019
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: BUILDING STUBOUT TO SEPTIC TANK
Wording Building Stubout shall be installed to allow gravity feed to the septic tank whose outlet shall be installed to enable connection to the existing stubout on the lot in order to assure fall to the existing tank to community drainfield.

Title: IMPERVIOUS %
Wording The UDC Administrator has approved a 47.8% maximum impervious surface coverage for parcel 9799001000 - Lot 37, per Jefferson County Code (JCC) 18.30.050, note 15 from table 6-1 as this lot was an existing legal lot of record. No additional impervious surface will be approved without the UDC administers review.

Title: PLANNER
Wording scc

Title: APPROVAL FOR NEW MAN. HOME ONLY
Wording This approval is for a manufactured home only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: SITE PLAN CHANGES
Wording The revised site plan as submitted with the new manufactured home application on May 6, 2019 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated May 14, 2019 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: CONFIRMED ESA'S
Wording The application was reviewed by the Jefferson County Department of Community Development staff on April 12, 2019 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review, the following ESAs were confirmed to be present on the subject property: critical aquifer recharge area

Title: CARA
Wording Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.

Title: MEDIUM STORMWATER
Wording The applicant is proposing to create or add 2700 square feet of impervious surface and 2097 square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require the project applicant submit a stormwater plan meeting Minimum Requirements #1 through #5 of the Department of Ecology Stormwater Management Manual for Western Washington. The stormwater plan shall address measures to control stormwater, erosion and sediment during construction and shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: STORMWATER PLAN
Wording A Stormwater Plan has been submitted and approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan. A Certificate of Occupancy will not be issued until the Department receives a letter from Anderson Civil Engineers and Surveyors that verifies plan compliance. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed.

Title: C-SWT CERTIFICATION
Wording PRIOR TO FINAL BUILDING OCCUPANCY, PROPONENT SHALL SUBMIT A WRITTEN LETTER FROM ANDERSON CIVIL ENGINEERS AND SURVEYORS STATING THAT THE STORMWATER FACILITY HAS BEEN CONSTRUCTED IN ACCORDANCE WITH THE REQUIREMENTS OF THE ENGINEERED PLAN SUBMITTED MAY 6, 2019 AND APPROVED MAY 14, 2019.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.